Permit Information
Permit NumberESC12-01119
StatusFinaled
Name BRYAN MURDOCH
Site Address 2810 E HARDROCK DR
Project Name 
Customer Number 
ePlanReviewNo
Description
Per the attached ESC conditions
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection10/24/201310/24/201310/24/2013 PASS
DetailsAndy J. Long
Finaled.
DOC - Permit Finaled10/24/201310/24/201310/24/2013PPASS
DetailsAndy J. Long
Construction complete, BLD permit already finaled and house is occupied. Homeowner has left straw wattles installed at the toe of slope while vegetation is establishing itself on hillside. Conditions have been met, no further ESC inspections required.
General Inspection9/23/20139/23/20139/23/2013 PASS
DetailsAndy J. Long
Construction is complete. Waddle lining street should remain until front bank is stabized. Site currently in good condition.
General Inspection8/22/20138/22/20138/22/2013 PASS
DetailsDaryl Spivey
General Inspection7/22/20137/22/20137/22/2013 PASS
DetailsKimberly M. Johnson
Final grading for landscaping in progress. Wattles may need replaced soon dependant on final stabilization method
General Inspection6/21/20136/21/20136/21/2013 PASS
DetailsClint A Smith
General Inspection5/21/20135/21/20135/21/2013 PASS
DetailsClint A Smith
General Inspection4/19/20134/19/20134/19/2013 PASS
DetailsClint A Smith
BMP Violation3/15/20133/18/20133/18/2013PPASS
DetailsEric Strole
corrections complete
BMP Violation3/15/20133/15/20133/15/2013PFAIL
DetailsEric Strole
Left verbal via voice mail and written correction to install sediment barriers along the front of project, clean up all dirt and debris off all hard surfaces and gutter pans, install concrete wash out being there is concrete residue in gutter pan all the way to the storm drain inlet and move port-a-pot off side walk and put in an approved location. Have complete by 3-18-13 am. Will reinspect on 13-18-13 pm.
BMP Violation3/7/20133/8/20133/8/2013APART
DetailsClint A Smith
Must still contruct a contained washout proir to the next pour date.
General Inspection3/7/20133/7/20133/7/2013 FAIL
DetailsClint A Smith
C/N Posted, Verbal to RP;

Clean up all concrete washout residual.
Provide a waashout for future use.
Clean up all hardsurfaces of all sediment and debris.
Failure to comply will result in further enforcement.
Will re-inspect on 3/8/2013
Site Preparation1/30/20132/4/20132/7/2013APART
DetailsClint A Smith
Verbal to RP;
providde a sediment brrier alond access by the end of work day.
Conference1/22/20131/29/20131/30/2013ACANC
DetailsClint A Smith
Moved to 2/4/2013 due to weather conditions.
General Inspection1/22/20131/22/20131/22/2013 PART
DetailsClint A Smith
Meeting with the RP on 1/28/2013