Permit Information
Permit NumberESC12-01216
StatusFinaled
Name TONY O'NEIL
Site Address 9052 W FAIRVIEW AVE
Project NameJack in the Box 6057
Customer Number 
ePlanReviewNo
Description
Development of a fast food restaurant (Jack in the Box) with a 24 hr. drive thru. The building will consist of approximately 2,479 S.F.and will be located at the parcel located at the corner of the intersection between Fairview Ave. and Maple Grove Rd. Site work will include landscaping, new paving for drive thru and walk ways, new trash enclosure, and parking spaces.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled1/8/20141/8/20141/8/2014PPASS
DetailsAndy J. Long
Unpaved area to the west of the Jack in the Box parking lot was previously a dirt lot before construction and was not part of project. Although on same parcel, it was not part of the area of disturbance. The lot has been graded and 3/4 inch gravel placed on the lot for stabilization in early December 2013. ESC conditions satisfied.
Site Final1/7/20141/8/20141/8/2014APASS
DetailsAndy J. Long
Site final requested. Chris Collete - Radix Construction ph # ###-####

Finaled. Please see activity notes.
General Inspection12/30/201312/30/201312/30/2013 PASS
DetailsAndy J. Long
General Inspection11/12/201311/12/201311/12/2013 PART
DetailsAndy J. Long
Jack in the Box is open for business and has a temporary C of O. The adjacent dirt lot is graded but there is no activity. The lot needs stabilization or restricted access to prevent track out to parking lot and street. See activity notes
Site Final9/26/20139/27/20139/27/2013PNR
DetailsJim Sly
Steve phone
Need to Stabilize all surronding disturbed areas.
Site Final9/25/20139/26/20139/26/2013PNR
DetailsJim Sly
Steve phone
Site Final9/25/20139/25/20139/25/2013PCANC
DetailsJim Sly
Tony phone
Site Final9/18/20139/19/20139/19/2013ANR
DetailsJim Sly
General Inspection9/16/20139/16/20139/16/2013 PASS
DetailsAlan Hauser
General Inspection7/30/20137/30/20138/1/2013 PART
DetailsKimberly M. Johnson
Met superintendent on site (Rick). Must adequately protect canal located on north side of property. Canal was not identified on plan set. Discussed with Rick the need to identify owner of canal company to ask what needs done within the canal co easement. Must install one more DI BMP on Maple Grove. Had DIs protected on Fairview and one on Maple Grove.
Site Preparation6/13/20136/13/20136/13/2013 PASS
DetailsClint A Smith