Aging Inspection | 9/15/2014 | 9/15/2014 | 9/15/2014 | | PASS |
Andy J. Long
|
|
|
All infrastructure and streets for Dallas Harris Estates phase 11 is complete with most parcels occupied or in progress with Tahoe Homes - all covered with sepearte ESC permits.
|
DOC - Permit Finaled | 9/15/2014 | 9/15/2014 | 9/15/2014 | P | PASS |
Andy J. Long
|
|
|
|
Random Inspection | 7/15/2014 | 7/15/2014 | 7/15/2014 | P | PASS |
Andy J. Long
|
|
|
Some survey work being conducted in Dallas Harris #11 for either more infrastructure or perhaps plotting the new parcels. No trackout or violations. Will continue to monitor activity.
|
Aging Inspection | 6/2/2014 | 6/2/2014 | 6/2/2014 | | PASS |
Andy J. Long
|
|
|
Some parcels remain open for new construction. RP for Tahoe Homes maintained DI on alley for phase 11. This permit is for the actual subdivision development/grading/paving by Knife River, but is open to keep an eye on this area of heavy construction and potential for ESC issues.
|
General Inspection | 3/31/2014 | 3/31/2014 | 3/31/2014 | | PASS |
Andy J. Long
|
|
|
This permit covers Block 36 and majority of house are permitted through Tahoe Homes. Streets, sidewalks, and gutters are clean. Stormwater catch basins have DI protection.
Approved.
|
General Inspection | 1/27/2014 | 1/27/2014 | 1/27/2014 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/25/2013 | 11/25/2013 | 11/25/2013 | | PASS |
Andy J. Long
|
|
|
Individual lots now have vertical construction. BMPs are installed. No further development under this permit, but will need to monitor stabilization.
|
General Inspection | 9/24/2013 | 9/24/2013 | 9/24/2013 | | NR |
Andy J. Long
|
|
|
phase 11 construction yet to begin
|
General Inspection | 7/24/2013 | 7/24/2013 | 7/26/2013 | | CANC |
Kimberly M. Johnson
|
|
|
|
General Inspection | 5/22/2013 | 5/22/2013 | 5/22/2013 | | NR |
Clint A Smith
|
|
|
activities on phase 11 have not begun
|
Site Preparation | 3/22/2013 | 3/22/2013 | 3/22/2013 | | PASS |
Rock A. Hudson
|
|
|
|