Site Final | 9/10/2015 | 9/10/2015 | 9/10/2015 | P | PASS |
Andy J. Long
|
|
|
All construction complete. Hillside have vegetated/stabilized. DI bags on Millet have been pulled as requested. Permanent stormwater features complete, all temp BMPs removed except a few degradable wattles on the upper hillside.
No further ESC inspections. Permit conditions satisfied.
|
Aging Inspection | 8/31/2015 | 8/31/2015 | 8/31/2015 | | PEND |
Andy J. Long
|
|
|
All construction in Tripplett townhome subdivision is complete. All temporary BMPs have been removed except for the two DI bags on Triplett.
Request to remove inlet bags issued in order to Final permit.
|
Aging Inspection | 6/29/2015 | 6/29/2015 | 6/30/2015 | | PEND |
Andy J. Long
|
|
|
All BMPs removed and hillside stabilized & vegetated. Townhome construction is complete.
1 remaining correction:
Remove DI bags on MS4 storm drains on main section of Millet.
Will advise Tahoe Homes and Conger Development.
|
Aging Inspection | 4/27/2015 | 4/27/2015 | 4/27/2015 | | PASS |
Andy J. Long
|
|
|
All Triplett townhome parcels are either occupied or vetical construction in progress. Subdivision BMPs installed, including wattles at the toe of slope along back of occupied homes.
No discharges, trackout, or other violations. There is several townhomes in center section that will be ready for final this week as they are being landscaped and cleaned.
|
Aging Inspection | 2/23/2015 | 2/23/2015 | 2/23/2015 | | PASS |
Andy J. Long
|
|
|
Triplett townhome sub is near completion with the last open parcels under construction. Hillsides that were regraded are now vegetateted. Will keep open until all activity is complete and temp BMPs are removed.
|
Aging Inspection | 12/22/2014 | 12/22/2014 | 12/22/2014 | | PASS |
Andy J. Long
|
|
|
Townhomes in progress. No drainage or hillside erosion problems occuring after long weekend rain.
Triplett Townhome sub not causing illicit discharges. Approved.
|
Aging Inspection | 10/20/2014 | 10/20/2014 | 10/20/2014 | | PASS |
Andy J. Long
|
|
|
Triplett Sub development phase is complete. Townhomes are in progress, upper view lots are vegetated. Rocky swale drainage is protected by well established grass and silt fence between the swale and the area of disturbance. Tahoe Homes is using a lined concrete washout pit.
No corrections at this time. Will keep permit open through completion of townhomes.
|
Aging Inspection | 8/18/2014 | 8/18/2014 | 8/18/2014 | | PASS |
Andy J. Long
|
|
|
Triplett Ranch individual townhomes in progress. Hillsides have stabilized/revegetated around the retaining wall. Will keep permit open to check up on temporary BMPs.
|
Aging Inspection | 6/16/2014 | 6/16/2014 | 6/16/2014 | | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 4/14/2014 | 4/14/2014 | 4/14/2014 | | PASS |
Andy J. Long
|
|
|
Triplett Subdivision BMPs in decent condition. Hillside vegetation is establishing well. Tahoe Homes currently working on individual lots with seperate ESC permits.
|
Random Inspection | 2/11/2014 | 2/11/2014 | 2/11/2014 | A | PASS |
Andy J. Long
|
|
|
Hillside inspection. Stabilization and BMPs installed are preventing erosion and trackout to Millet. No large rills or other issues observed. Approved.
|
Aging Inspection | 1/15/2014 | 1/15/2014 | 1/15/2014 | | PASS |
Andy J. Long
|
|
|
No hillside erosion or channel washouts observed - stabilization and hillside drainage divirsion appear effective. Perimter BMPs prevented muddy runoff onto streets at east end. Some stockpiles in middle of site currently. No corrections at this time.
|
BMP Violation | 11/14/2013 | 11/15/2013 | 11/15/2013 | A | PASS |
Andy J. Long
|
|
|
Clint from Tahoe Homes (2 active sites) will place wattles at foot of silt fence. Existing stormwater trench with check dams will capture majority of runoff.
Clint stated fences are to keep contractors/public from driving on and off lots. Crew will install wattles at low spots and sweep roads.
Will check for corrections next inspection in Triplett Ranch.
|
General Inspection | 10/29/2013 | 10/29/2013 | 10/29/2013 | | PASS |
Andy J. Long
|
|
|
Sudvision development in progress. Some individual sites have began. BMPs implemented and no track out to main part of Millet. The silt fence at east in by sign needs to be trenched in, but after storm yesterday site conditions are approved.
|
BMP Violation | 8/23/2013 | 8/27/2013 | 8/27/2013 | A | PASS |
Eric Strole
|
|
|
|
BMP Violation | 8/22/2013 | 8/23/2013 | 8/23/2013 | P | FAIL |
Eric Strole
|
|
|
Left verbal and written correction that all corrections on previous correction need complete by 8-26-13 pm or a stop work will be issued. Only corrections complete are pot-a-pot moved, concrete cleaned up and esc sign moved. Will reinspect on 8-27-13 am
|
BMP Violation | 8/21/2013 | 8/23/2013 | 8/22/2013 | P | CANC |
Eric Strole
|
|
|
|
General Inspection | 8/21/2013 | 8/21/2013 | 8/21/2013 | | FAIL |
Eric Strole
|
|
|
Left verbal via voice mail and written correction to post esc sign to be visible from street, move port-a-pot off sidewalk, clean up all dirt and debris off all hard surfaces and gutter pans, clean up all concrete tha was washed out on ground and install concrete washout pit, protect di's and maintain and protect drainage swall. Have complete by 8-23-13 am. Will reinspect on 8-23-13 pm.
|
Complaint Inspection | 6/17/2013 | 6/17/2013 | 6/17/2013 | A | DONE |
Clint A Smith
|
|
|
No water truck on site and could not reach the RP. Explained to the RP's company to discuss the issue with the grading company and surpress the dust with water at the least
|
Conference | 5/7/2013 | 5/7/2013 | 5/8/2013 | P | DONE |
Kimberly M. Johnson
|
|
|
Pre-con with Jim Cosslett, Jim Wylie, Jason Taylor, Kelly from Conger Management Group and Jim from Excavator company. wattles installed on north side; ESC sign posted and DI BMPs staged onsite. Excavator will install construction entrance first. Discussed need to monitor straw wattles closely since there is not room for a buffer and construction will need to disturb directly adjacent to them. Also discussed need for all operators to file and NOI.
|