Site Final | 4/11/2017 | 4/14/2017 | 4/14/2017 | A | PASS |
Melissa Jannusch
|
|
|
Preformed site walk through with Corey. All earth disturbing activities are complete. Soil is stable. DI bags and temporary BMPs have been removed. The drainage channel to Logger’s creek is complete and stabilized. Drainage pavers appear to be working. Staging area has been cleaned and no equipment has been left behind. No windblown trash around the site. Gave Colby information on filing the NOT for the CGP permit. Ok to final.
|
General Inspection | 4/10/2017 | 4/10/2017 | 4/10/2017 | P | PASS |
Melissa Jannusch
|
|
|
Landscaping complete. Need to sweep staging area and remove equipment before permit can be finaled.
|
General Inspection | 4/5/2017 | 4/5/2017 | 4/5/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/21/2017 | 3/21/2017 | 3/23/2017 | | PASS |
Melissa Jannusch
|
|
|
Inspection conducted on 3/22/2017. Project nearing completion. Staging area is clean. Most soil is stabilized with bark chips and shrubs. Project okay.
|
General Inspection | 3/6/2017 | 3/6/2017 | 3/6/2017 | | PASS |
Melissa Jannusch
|
|
|
Soil has been stabilized with bark chips and landscaping. Some work still in progress. Staging area is clean. No trackout observed. No corrections requested.
|
General Inspection | 2/17/2017 | 2/17/2017 | 2/17/2017 | | PASS |
Melissa Jannusch
|
|
|
Okay. Final stabilization has not been reach. No trackout, staging area clean.
|
General Inspection | 2/2/2017 | 2/2/2017 | 2/3/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/18/2017 | 1/18/2017 | 1/23/2017 | | PASS |
Melissa Jannusch
|
|
|
No earthwork occuring. Snow covered. Staging along SE side of site. No trackout.
|
General Inspection | 1/3/2017 | 1/3/2017 | 1/4/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/19/2016 | 12/19/2016 | 12/19/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/2/2016 | 12/2/2016 | 12/2/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/17/2016 | 11/17/2016 | 11/18/2016 | | PASS |
Andy J. Long
|
|
|
Both entrances now paved, no trackout to Parkcenter and interior surfaces and drainages to the permeable pavers have been swept and not dirt stockpiles. WIP on southwest corner of project including landscaping. Silt fence along Loggers Creek has been removed where landscaping/stabilization has been installed behind condo units. No corrections requested at this time.
|
General Inspection | 11/2/2016 | 11/2/2016 | 11/4/2016 | | PASS |
Andy J. Long
|
|
|
WIP on southeast portion of project. Frontage and swale are now landscaped. No trackout to Parkcenter. Trash and materials being contained. Unfinished areas of permeable pavers are protected. No corrections requested.
|
General Inspection | 10/18/2016 | 10/18/2016 | 10/20/2016 | | PASS |
Andy J. Long
|
|
|
WIP on site improvement and units on the south west side of site. Main entrance is paved; newly installed swale along Parkcenter has been sodded and curb cut inlets cleaned. Minor trackout to road apron at the auxiliarry construction exit, no muddy trackout.
WIP. No corrections at this time
|
General Inspection | 10/3/2016 | 10/3/2016 | 10/3/2016 | | PART |
Andy J. Long
|
|
|
Construction and site development in progress on south-east side of site. North west and main entrance is now paved, partially landscaped, and some units are occupied. No significant spills, loose trash or dust issues observed. Concrete washout pan located near unpaved construction entrance. Landscaping around open irrigation ditch area has not yet started. Water still flowing in ditch. The outlet to Loggers Creek has been re-routed in a lined channel to stay on The District Property. Water looks clear and does not appear to be loading sediment from construction acitivity.
Corrections: - Sweep up apron to Parkcenter or have plan to install trackout controls . Provide paving schedule - Curb cut inlet to new swale along Parkcenter need cleaning/mainteance.
Verbal corrections discussed with RP Cory.
|
Site Preparation | 9/15/2016 | 9/16/2016 | 9/16/2016 | A | CANC |
Andy J. Long
|
|
|
data entry error, disregard
|
General Inspection | 9/15/2016 | 9/15/2016 | 9/15/2016 | | CANC |
Andy J. Long
|
|
|
|
Random Inspection | 8/31/2016 | 8/31/2016 | 8/31/2016 | P | PASS |
Scott Arellano
|
|
|
No track out observed, waddles, signage, construction entrance in satisfactory condition.
|
General Inspection | 8/25/2016 | 8/25/2016 | 8/25/2016 | | PASS |
Andy J. Long
|
|
|
Paved main entrance is now open. WIP on landscaping and site improvement on the frontage and within the development. No trackout or fugitive dust observed.
|
General Inspection | 8/10/2016 | 8/10/2016 | 8/10/2016 | | PASS |
Andy J. Long
|
|
|
No trackout, construction entrance installed. Main entrance is paved and blocked off to constrution traffic. WIP on interiors, site improvements, and frontage landscaping. No violations observed.
|
General Inspection | 7/26/2016 | 7/26/2016 | 7/26/2016 | | PASS |
Andy J. Long
|
|
|
Interior work and site development occuring at the District @ Parkcenter.
Main entrance is now paved and trackout controls removed. Construction entrance still installed at the alternative site access. Not all access lanes and parking areas are paved yet.
No trackout to street, no significant amounts of sediment from site accumulated in gutter. Trash and liquid waste properly contained onsite. RP conducting regular SWPPP inspections for SWpPP binder.
No corrections issued.
|
General Inspection | 7/11/2016 | 7/11/2016 | 7/11/2016 | A | PASS |
Andy J. Long
|
|
|
WIP. No trackout. No fugitive dust occuring. BMPs installed. Perimeter is clean, trash and materials contained in site. Washout and liquid waste boxes provided.
|
Conference | 6/29/2016 | 6/29/2016 | 6/29/2016 | A | DONE |
Andy J. Long
|
|
|
Notified to change RP from Kevin to Cory. Cory onsite and certified RP. Approved
|
General Inspection | 6/27/2016 | 6/27/2016 | 6/27/2016 | | PASS |
Andy J. Long
|
|
|
WIP on interior of aparment complex and roofing. No earthwork, no changes to irrigation ditch outlet and no issues or plume or observed at Logger's Creek.
Trackout controls (rock entrance, rumble bars) are installed at both access points. No fugitve dust or construction debris leaving site. No corrections at this time.
|
General Inspection | 6/10/2016 | 6/10/2016 | 6/10/2016 | | PASS |
Andy J. Long
|
|
|
WIP on apartment building interiors. Site improvements and landscaping on exterior should be coming soon. Trackout and perimeter control are working well. No corrections.
|
General Inspection | 5/26/2016 | 5/26/2016 | 5/26/2016 | | PASS |
Andy J. Long
|
|
|
WIP. Project to conduct fire line flushings, an allowable discharge. Water to be directed toward silt fence and vegetated buffer along Logger's Creek. Water should infiltrate before reaching creek, but requested flushing be stopped if a plume is visible.
No violations observed.
|
General Inspection | 5/11/2016 | 5/11/2016 | 5/11/2016 | P | PASS |
Andy J. Long
|
|
|
Notified by RP that new construction entrance has been installed to accomodate trucks entering from east Parkcenter. Rock is heavy duty 3-4 inch angular.
No trackout from site, street and gutter has been swept last week. BMPs of concrete washout bin, designated waste management areas, and lined irrigation channel are in good condition.
Approval has been granted by irrigation district to the project owners to re-routing outflow of lateral to not cross private property of the existing home and stabilize the area to prevent future bank erosion or neighbor conflict. Discharge of the irrigation water is clear in Loggers Creek, bank is stable.
|
Complaint Inspection | 4/27/2016 | 4/27/2016 | 4/27/2016 | A | PASS |
Andy J. Long
|
|
|
Complaint about damage to Logger's Creek bank and private property; second complaint response by ESC inspector(s) regarding the issue.
ESC division inspected area of irrigation water discharge at 9:45 AM. Water from a South Boise Irrigation ditch lateral is passing through site via pipe and lined pond area (to be landscaped). Design has been approved by the irrigation company per ESI.
No stormwater or dewatering from the site is going into the ditch. The water exiting the site from the ditch is visibly clear. After passing through the site perimeter silt fence the water flows over a grassy bank and some small washed river rock to line a section of the channel. The water does flow over some grass and several concrete bank stabilization blocks installed prior to construction activity. The vegetation on the bank has been preserved with the bank buffer zone between silt fence and creek. The flow of the ditch water may pass over a corner of the neighboring private property, unclear at time of inspection the exact boundaries. The irrigation district water master has been alerted of the situation, but the water has not been able to be shut off at this point.
Recommend that when project is landscaped/stabilized and silt fence removed and irrigation flow is less, that all construction materials (stakes, river rock) and other items be removed and irrigation ditch outlet either stabilized or allowed to revegetate.
No significant bank erosion was discovered, no turbid plume of water in Logger's Creek is observable. The occurrence is a non-turbid non-stormwater discharge not related to construction, and is not in violation of the City of Boise ESC permit.
Note: prior to development irrigation ditch was not piped and flowed into site to a pond/wetland area with an overflow connection to Loggers Creek. Water now does not infiltrate and is returning to the Creek.
|
Complaint Inspection | 4/22/2016 | 4/22/2016 | 4/22/2016 | P | PASS |
Andy J. Long
|
|
|
Complaint received about bank erosion on Logger's Creek caused by the irrigation water passing through site....
Inspected area of irrigation water discharge along the bank. No channel or consruction area has disturbed the vegetative buffer zone. Through the site, the water passes through the construction area via pipe and then a lined channel. The water is not visibly turbid when exiting the site. At the site perimeter and creek bank, water passes through the original silt fence to a river-rocked channel and then through the grass on the bank. It appears some concrete gabions were placed there by the irrigation district in the past to stabilize the bank.
No plume seen in the creek. Some sand deposited on creek bottom right at discharge.
While at site observed contained trash & materials, lined & designated liquid waste washout box, construction entrance, and minimal accumulations of sediment and sand from site on Parkcenter. No fugitve dust.
No violation, the irrigation water through site does not add turbidity due to construction. The water historically discharge in this area, but currently flows are high because of high river water, low irrigation use, and the District irrigation system is not online yet. Flows should decrease soon and perhaps stop passing over bank area. No significant bank damage or impacts to water quality discovered. Recommended having the irrigation district watermaster come take a look as well.
|
General Inspection | 4/15/2016 | 4/15/2016 | 4/15/2016 | | PASS |
Evan Jenkins
|
|
|
WIP: no discharges leaving the site at this time
|
General Inspection | 3/31/2016 | 3/31/2016 | 3/31/2016 | P | PASS |
Andy J. Long
|
|
|
Conference inspection requested to inspect area where swale and water feature is to be installed conducted. Irrigation water will start to flow through this area this weeked due to early strart of season.
To limit the disturbance by the flow, requested that the piped irrigation outlet discharge into a section of rip rap before entering the the swale currently being excavated. The swale will infiltrate and settle some of the water and overflow from swale will going into a river-rocked spillway to the vegetated bank and flow into Logger's Creek. I requested that the initial flow be monitored to check for turbidity issues and possible corrections.
RP stated that Parkcenter gutters in both directions will be swept by a street sweeper tomorrow.
Will check back early next week to check on the swale area
|
General Inspection | 3/21/2016 | 3/21/2016 | 3/21/2016 | | PASS |
Andy J. Long
|
|
|
WIP. Site perimeter BMPs are installed. Stormwater pollution prevention team onsite at all times during construction. No significant trackout, construction entrance and rumble bars are currently in good condtion.
No corrections issued. Approved.
|
Tracking Control | 3/4/2016 | 3/4/2016 | 3/4/2016 | P | PASS |
Andy J. Long
|
|
|
Apron from construction entrance to Parkcenter was swept up as requested. A street sweeper with hit the areas in front of curbs and curb cutter later today or this weekend due to high traffic on Parkcenter.
|
Tracking Control | 3/2/2016 | 3/2/2016 | 3/2/2016 | P | PART |
Andy J. Long
|
|
|
Correction request to sweep the paved apron between the tracking pad and ROW.
Streets are being swept 1x per week and apron swept as needed. Requested that it be swept at a minimum of once a week and more if trackout is occuring.
|
General Inspection | 2/23/2016 | 2/23/2016 | 2/24/2016 | | PASS |
Andy J. Long
|
|
|
Construction entrance and rumble bars are limiting trackout. No sediment or discharges leaving site. Housekeeping and waste management is in compliance. Approved.
|
General Inspection | 2/8/2016 | 2/8/2016 | 2/8/2016 | | PASS |
Andy J. Long
|
|
|
WIP. No trackout from site. No changes to perimeter sediment control. No corrections at this time.
|
General Inspection | 1/22/2016 | 1/22/2016 | 1/22/2016 | | PART |
Andy J. Long
|
|
|
Verbal correction issued to RP -
sweep up trackout on paved entrance apron and on sidewalks. Clean off tracking plate to prepare for future precipitation and muddy conditions. Today is nice and dry.
RP stated it will be done before the end of the day.
|
General Inspection | 1/7/2016 | 1/7/2016 | 1/7/2016 | | PASS |
Andy J. Long
|
|
|
WIP on foundations and frames for buildings at the District. BMPs include silt fence perimeter and vegetative buffer between site and Logger's Creek (channel of river), trackout controls (large rock entrance, small rock at intersection, rumble bars), and concrete washouts.
Spill containment area around fuel tank is in good condtion.
No violations observed, SWPPP info posted. No corrections at this time.
|
General Inspection | 12/23/2015 | 12/23/2015 | 12/23/2015 | A | PASS |
Andy J. Long
|
|
|
WIP on vertical construciton. Trackout controls and site perimeter sediment controls are working well to keep dirt on site. No discharges observed or reported.
Approved, no corrections at this time.
|
Site Preparation | 12/21/2015 | 12/22/2015 | 12/23/2015 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/21/2015 | 12/21/2015 | 12/21/2015 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 12/4/2015 | 12/4/2015 | 12/4/2015 | | PASS |
Evan Jenkins
|
|
|
Construction entrance is proving very successfull even with the recent rains. No work occuring at this time throughout the project. No ESC issues observed
|
Tracking Control | 11/18/2015 | 11/19/2015 | 11/19/2015 | A | PEND |
Andy J. Long
|
|
|
Substantial rock construction entrance and rumble bars are installed but there is still some degree of trackout occuring.
ESI in process of ordering more rock for round about and parking in front of job trailer.
Sediment check dams installed in new shallow DIs to swale along Parkcenter. Treating runoff but requested installation of filter fabric under rock bags to trap more fines.
Will check back on conditions next week but trackout controls are as prescribed but need further improvement and increased broom sweeping on the paved apron.
|
General Inspection | 11/3/2015 | 11/4/2015 | 11/4/2015 | A | PASS |
Andy J. Long
|
|
|
930-10 AM discuss BMPs for newly installed swales
New sand window swales have been installed between sidewalk and Parkcenter Blvd. The inlet are curb cuts with shall basins and concrete downspouts into swale . To protect swales, sand/rock bags will filter water through the spout.
Parkcenter roadway improvements are to be completed today, roadway will be swept and all 3 lanes will be opened. Entrance to the District is now paved, RP stated a new rock construction entrance will be installed behind paved portion to control trackout from material trucks and employee parking.
Former irrigation collection pond has now been filled in and buildings are in progress in the area. Stormwater that has drained into irrigation ditch/box is being pumped over to old groundwater discharge treatment area. Very low flow, no turbidity observable in Loggers Creek. Silt fence perimeter protecting the waterway is in good condition and no breaks found.
Lined concrete washoul box located in center of project with signage is in use and no significant leaks or failures. Trash management is acceptable, no windblown litter or material wrappings.
No corrections at this time. Site will be in good condition after final sweeping this afternoon on Parkcenter.
|
General Inspection | 10/30/2015 | 10/30/2015 | 10/30/2015 | | PASS |
Andy J. Long
|
|
|
WIP. Entry road apron for the District is near completion. Parkcenter median has been swept, no significant trackout occuring currently. RP onsite. No corrections at this time.
|
General Inspection | 10/15/2015 | 10/15/2015 | 10/15/2015 | | PASS |
Andy J. Long
|
|
|
No significant trackout from site, water trucks circling periodically on roads for dust control within site.
Irrigation water is no longer running through site and discharging to Boise River channel. Groundwatering is complete as well.
RP stated entry roads are to be paved next week and he will provide a stabilzed parking area for workers to prevent trackout and creation of puddles in parking lots. Concrete washouts are being utilized.
Approved.
|
BMP Violation | 9/30/2015 | 9/30/2015 | 9/30/2015 | P | PASS |
Evan Jenkins
|
|
|
concrete washouts reported to be full and spilling..
RP Kevin ###-####
2 new concrete washouts have been installed right before I got there. no other issues observed
|
Conference | 9/21/2015 | 9/21/2015 | 9/21/2015 | P | DONE |
Andy J. Long
|
|
|
Irrigation water receiving pond was used to collect United Water mainline flushing at the District at Parkcenter. Earlier today an earthen berm was broken by an excavator mistakenly and there was a turbid discharge of the water reported by ESI into Logger's Creek.
The flow was stopped and ESI reported there was no visible plume by 2:45 PM. I requested that the excavator receive further training on permitted discharges and pollution prevention.
Note: Irrigation water still passing through site and into Logger's Creek. No groundwater dewatering or other disharges are occuring.
|
General Inspection | 9/15/2015 | 9/17/2015 | 9/17/2015 | A | PASS |
Andy J. Long
|
|
|
WIP. No trackout to Parkcenter or muddy runoff from site. No dewatering currently. Site walk through to be conducted tomorrow or next week
|
General Inspection | 9/15/2015 | 9/15/2015 | 9/15/2015 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 8/28/2015 | 8/31/2015 | 8/31/2015 | A | PASS |
Andy J. Long
|
|
|
WIP on foundations and utility installations for apartment buildings in the District @ Parkcenter. No active dewatering at time of inspection. Irrigation ditch was rerouted from the former infiltration/holding pond (which is being drained and replaced per plans) and is flowing into Loggers Creek. There is no significant plume observed and water passes through silt fence barriers, check dames, undisturbed stream bank vegetation and straw wattle. I stated that the discharge should be monitored several times daily turbidity measurements taken when dewatering.
No trackout, construction entrance in operable condition. New wattles have been installed along the project frontage on Parkcenter inside chainlink fence. Fuel tank secondary containment is in good condtion; spill kit on site.
No corrections issued.
|
General Inspection | 8/28/2015 | 8/28/2015 | 8/28/2015 | | CANC |
Andy J. Long
|
|
|
rescheduled for Monday
|
Conference | 8/12/2015 | 8/12/2015 | 8/12/2015 | P | PEND |
Andy J. Long
|
|
|
checking current dewatering system and log of turbidity measurements; visual check for plume...
After inspection, dewatering from irrigation pond has been halted to increase settling time for groundwater dewatering.
Going to postpone pond dewatering while groundwater dewatering is occuring.
|
General Inspection | 7/31/2015 | 7/31/2015 | 7/31/2015 | | PASS |
Andy J. Long
|
|
|
No trackout from site. No fugitve dust issues observed or reported. No dewatering currenting. WIP. No corrections at this time.
|
General Inspection | 7/16/2015 | 7/16/2015 | 7/16/2015 | | PASS |
Andy J. Long
|
|
|
Site RP and superindentant is onsite. Entrance area was stabilized with asphalt to prevent track out.
Full site walk through conducted. Site perimeter silt fence and chainlink fencing are in good condition. Lined concrete washout containers are being utilized. No issues at secondary containment area for fueling, no dewatering occuring and no other discharges to Parkcenter or to Logger;s Creek channel of Boise River. No corrections at this time.
|
General Inspection | 6/30/2015 | 7/1/2015 | 7/1/2015 | A | PASS |
Andy J. Long
|
|
|
No activity at site. No fugitive dust and no dewatering occuring. Will check back....no corrections or issues at this time.
|
General Inspection | 6/30/2015 | 6/30/2015 | 6/30/2015 | | CANC |
Andy J. Long
|
|
|
walk through scheduled for tomorrow AM
|
General Inspection | 6/15/2015 | 6/15/2015 | 6/16/2015 | | PASS |
Evan Jenkins
|
|
|
WIP: no issues at this time
|
Complaint Inspection | 5/29/2015 | 5/29/2015 | 5/29/2015 | P | FAIL |
Evan Jenkins
|
|
|
New well point to begin sewer trenching is pumping turbid water throughout their system, discharging into loggers creek. Contractor to submit new dewatering plan utilizing a filtration system before more work to be performed
|
Complaint Inspection | 5/28/2015 | 5/28/2015 | 5/28/2015 | P | FAIL |
Evan Jenkins
|
|
|
Turbid Discharge into Loggers Creek Complaint
Discharge was 28 NTU's above loggers creek background. Contractor diverted discharge from loggers creek into a large detention pond. Dewaterinng should be complete this afternoon. Will follow up tomorrow Temp SWO was issued on Dewatering activities until they dug a new dewatering trech lined with gravel check dams into detention pond
|
BMP Violation | 5/22/2015 | 5/22/2015 | 5/22/2015 | P | PEND |
Andy J. Long
|
|
|
Combination of stormwater from yesterday's rain event, irrigation water, and water accumulated from previous dewatering was about to overflow pond into private residence. Channel opened up to let water flow into Logger's Creek (channel of the Boise River). Water flowing was visibly turbid upon arrival.
No dewatering is occuring and flow has stoped. A lined channel with multiple check dams is treating/detaining water.
Working on setting up new settling pond system . A wier tank may be required.
Having ESC take turbidity samples and filing corrective action report in SWPPP.
|
General Inspection | 5/21/2015 | 5/21/2015 | 5/21/2015 | P | PASS |
Andy J. Long
|
|
|
Dewatering has been post poned to allow ponds to infiltrate/drain so they can been lined and improved. Water is too murky & turbid to discharge. Water truck is pumping water out of the pond to use for fugitive dust control.
ESI will contact next week when proper setup is constructed. Approved.
|
General Inspection | 5/20/2015 | 5/20/2015 | 5/20/2015 | P | PASS |
Andy J. Long
|
|
|
1:30 PM to discuss and review dewatering plan and CGP permit requirements for monitoring
Two settling ponds are in use. No discharge to Logger's Creek occuring. Plan is to excavate a 3rd retention/infiltration pond to increase settling time. In addition to settling pond, water is to be used for dust control and pumped into a sprinker system along the stockpiles and areas not under construction.
ESI crew is,putting the plan on paper for SWPPP, preparing to initiate the plan, and has read CGP to know monitoring and book keeping requirements.
|
Conference | 5/14/2015 | 5/14/2015 | 5/14/2015 | A | PEND |
Andy J. Long
|
|
|
meeting to discuss dewatering plans; requested for 8:45
Big Bite Inc., utilities installer will be doing the work at the District for ESI, starting at the end of May (after Memorial Day). Plan is to use frac tank /sediment box to treat pumped groundwater. The water will then discharge into a trench that flows around site perimeter to the approx. 1 acre pond. This pond does not have an outlet pipe and a discharge to Boise River /Logger's Creek is not anticipated.
Requested that written plan modification be submitted to PDS and include:
1. Change RP name (Kevin Honeycutt) 2. Dewatering plan narrative (construction schedule, pump rates, treatment details, inspection frequencie, corrective action plan, etc) and site map
Conditions at site are currently in compliance. BMPs include stabilized construction entrance, perimeter controls, fuel station with secondary containment, and water truck for dust control.
No dewatering until plans are submitted and approved.
|
Conference | 5/5/2015 | 5/5/2015 | 5/5/2015 | P | DONE |
Andy J. Long
|
|
|
ESI foreman Kevin Honeycutt called to notify me that he can be contacted for ESC corrections and issues at District site. # ###-####
|
Random Inspection | 4/29/2015 | 4/29/2015 | 4/29/2015 | A | PEND |
Andy J. Long
|
|
|
Site grubbing and initial grading has started. Discussed operations with superindendent Igor with ESI and Mike with Spiers Construction. Conducted full site walk through.
Silt fence perimeter lines the river channel to the southwest of the site. Silt fence is wire backed and properly trenched in. There is a 30-45 ft vegetative buffer along the stream channel.
There is a irrigation ditch the runs to a holding pond at southwest corner of site. It does not discharge into stream channel. ESI/Spiers working with irrigation district to use water for dust suppression and other needs. No trackout or significant dust issues yet, but requested:
1. Install construction entrances (x2). Scheduled for tomorrow. 2. Water truck needs to be onsite for fugitive dust control. Requested that should be on site this afternoon/ASAP. Some small plumes of dust intermittently cross Parkcenter and today is windy. 3. Mike from Spiers is going to call me to inspect secondary containment area for equipment fueling station. I stated needs to contain 110% volume of tank and being lined. Mike will like it with vapor barrier and cover with 3" sandy soils to avoid puncture.
Approved to proceed with operations. Status pending based on water truck and construction entrances.
|
Site Preparation | 4/24/2015 | 4/24/2015 | 4/24/2015 | P | PEND |
Andy J. Long
|
|
|
Site walk through to occur next week. Perimeter BMPs, construction fencing, and silt fence along creek channel have been installed. Some minor site grubbing/exploration has occured. No issues at site. Will check back next week.
|
General Inspection | 4/22/2015 | 4/22/2015 | 4/22/2015 | | PASS |
Andy J. Long
|
|
|
No earthwork or other activity yet at site. Some heavy equipment has been parked in center of area to be developed. ESI contact stated that they would call me for site prepartion inspection once BMPs are installed. Approved
|
General Inspection | 4/7/2015 | 4/7/2015 | 4/7/2015 | | PASS |
Andy J. Long
|
|
|
The District at Parkcenter has not yet started. No BMPs or permit signage. Will check for start time and schedule site prep inspection. Multilbuilding complex with ESC14-00588 to ESC14-00602
|