Permit Information
Permit NumberESC14-00885
StatusFinaled
Name RANDY REUTZEL
Site Address 3900 S ECKERT RD
Project NameEckert Road Greenbelt
Customer Number 
ePlanReviewNo
Description
Stormwater Pollution Prevention Plan for Eckert Road Pathway
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection6/16/20156/16/20156/16/2015 PASS
DetailsEvan Jenkins
DOC - Permit Finaled6/16/20156/16/20156/16/2015APASS
DetailsEvan Jenkins
Vegetation Re-established
ESC Conditions Satisfied
General Inspection6/1/20156/1/20156/1/2015 PASS
DetailsEvan Jenkins
General Inspection5/15/20155/15/20155/15/2015 PASS
DetailsAndy J. Long
Vegetation on the shoulders of path has established and path has been open to public for some time. Some temp wattles are still installed drainage and culvert structures. Permit should be ready to close next inspection and assess whether BMPs may remain or be removed.

Checked discharge from Council Springs Creek into the Boise River by the Eckart bridge (creek channel passess through construction site) during rain event and it clear and not turbid.
General Inspection4/30/20154/30/20154/30/2015 PASS
DetailsAndy J. Long
Greenbelt path complete and in use. Shoulders have been hydroseeded and vegetation is still establishing. Next inspection will check to see if disturbed areas are stabilized and temp BMPs may be removed.
General Inspection4/15/20154/15/20154/15/2015 PASS
DetailsEvan Jenkins
Minimal Vegetation Growth. It appears to be volunteer growth, not from the hydroseeding.
No ESC issues at this time
General Inspection3/27/20153/27/20153/27/2015 PASS
DetailsAndy J. Long
Construction complete on Eckert Greenbelt path. The shoulders/disturbed area has been hydoseeded but is not established yet. Will continue to monitor. No corrections at this time.
Aging Inspection2/19/20152/19/20152/23/2015 PASS
DetailsAndy J. Long
Greenbelt Path is complete and open to public. Shoulders have not yet been seeded or stablized. No flow through Council Springs Creek culverts currently. No trackout, dust issues, or turbid discharges. Need to check on plans for revegetation.
Random Inspection12/19/201412/19/201412/19/2014APASS
DetailsAndy J. Long
Greenbelt expansion path has been completed, including culvert installation for the two Council Springs Creek road crossings.

Final grading is in progress and the bare ground has not yet been hydroseeded or tacified. No major trackout. No water running in creek currently. Minimal activity at time of inspection.
General Inspection10/15/201410/15/201410/15/2014PPASS
DetailsAndy J. Long
Eckert path is in progress. Council Springs creek crossings have perimeter protection and gravel bags to trap sediment at outlet. No erosion issues.

Yesterday observed several spots where cement trucks washed out without containment. Called project manager/coordinator Jeff and requested that washout be conducted in a designated area. Knife River stated they will have trucks washout at DH #12 facility. Today no new washouts observed/no acitivity. Will continue to monitor.
BMP Violation9/26/20149/26/20149/26/2014APASS
DetailsAndy J. Long
Corrections at Eckart Greenbelt path have been completed.

1. Additional wattles have been installed at the south channel/culvert of Council Springs Creek to prevent sediment runoff from running into the stream.
2. Gravel bags have been laid flat on culvert inlets to create filter and settling time for sediment.

3. Gravel bag put at the inlet of the north culvert near Lucky Harris construction entrance.

Other:
Water truck was onsite to keep down dust. The two channels may be diverted so that when the path crosses the creek they can stop flow.

Approved.

Site Preparation9/24/20149/25/20149/25/2014APART
DetailsAndy J. Long
Eckart Greenbelt Path

Permit posted, SWPPP/NOI # onsite (no updates or inspection reports included), no dust issues or trackout to Eckart at time of inspection.

Note: No site prep inspection to inspect BMPs was requested as required.

Corrections:

1. Properly stake in loose wattles that are installed.
2. No inlet protection as indicated on site map for the culvert conveying the north channel of Council Springs Creek.
3. Unprotected and disturbed banks along the south channel crossing of of Council Springs Creek . 150-200 meters away from outlet to Boise River.

Notified Jeff at Knife River of issue as well as Syman Company of the problem and requested corrections. Rain forecasted for this weekend so requested corrections before weekend.