DOC - Permit Finaled | 12/1/2014 | 12/1/2014 | 12/1/2014 | P | PASS |
Andy J. Long
|
|
|
Pipeline project on eastern edge of airport area is complete and site returned to preexisting condtions. Temp BMPs have been removed and construction complete.
|
Random Inspection | 10/21/2014 | 10/21/2014 | 10/21/2014 | P | PASS |
Andy J. Long
|
|
|
Utility trenching project by Earth Energy along Production street is in progress. No trackout or other ESC violations. WIP. Permit is posted.
|
Site Preparation | 9/30/2014 | 9/30/2014 | 9/30/2014 | P | PASS |
Andy J. Long
|
|
|
Earth Energy on site making preparations for utility project. No MS4 or surface waters in project area. Drainage flows to airport's perimeter berm & swale. Approved.
|