Permit Information
Permit NumberESC15-00031
StatusFinaled
Name ED CONNELL
Site Address 6968 N BOGART LN
Project NameFAIRMONT SQUARE
Customer Number 
ePlanReviewNo
Description
per Jason Taylor no grading permit required 1-16-15 blh
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final3/23/20173/23/20173/23/2017APASS
DetailsAndy J. Long
Subdivsion fully developed and stabilized. Site permanent stormwater swales and infiltration pond are operational. Common areas landscaped. All homes complete and most occupied. Damage filter fabric in inlets on Elmbrook to be removed by HOA.
General Inspection3/10/20173/10/20173/10/2017 CANC
DetailsAndy J. Long
General Inspection1/23/20171/23/20171/23/2017 CANC
DetailsAndy J. Long
General Inspection12/6/201612/6/201612/6/2016 CANC
DetailsAndy J. Long
General Inspection10/21/201610/21/201610/21/2016 CANC
DetailsAndy J. Long
General Inspection9/5/20169/5/20169/5/2016 CANC
DetailsEvan Jenkins
holiday
General Inspection7/21/20167/21/20167/21/2016PPASS
DetailsEvan Jenkins
work occuring on various SFH's. No issues observed at this time
General Inspection6/24/20166/24/20166/24/2016 PASS
DetailsEvan Jenkins
No issues observed at this time
BMP Violation5/9/20165/9/20165/9/2016AFAIL
DetailsAndy J. Long
No lined concrete washout provided.

Correction request to builders and developer to provide a lined and designated concrete washout pit.

Check storm drain inlets for DI bag maintenance.
General Inspection5/3/20165/3/20165/3/2016 CANC
DetailsAndy J. Long
General Inspection3/18/20163/18/20163/18/2016 PASS
DetailsEvan Jenkins
sfh construction occuring. no issues observed at this time
General Inspection2/1/20162/1/20162/1/2016 PASS
DetailsEvan Jenkins
WIP: No ESC Violations observed at this time
Random Inspection12/16/201512/16/201512/16/2015PPASS
DetailsAndy J. Long
WIP on SFHs in Magnolia Park (formerly Fairmont Square). No sediment runoff from open lots. Permanent stormwater facilities are working properly and no discharges offsite. Builders parking on street to prevent trackout.

No corrections at this time
General Inspection11/16/201511/16/201511/16/2015 PASS
DetailsAndy J. Long
WIP on SFHs in Fairmont Square. Permanent stormwater controls and subdivision landscaping are complete. No erosion issues observed of drainage failures.

Home builders are keeping off open lots, no major trackout or loose sediment. Trash containment is provided. No spills or discharges observed. Approved.
General Inspection9/30/20159/30/20159/30/2015 PASS
DetailsAndy J. Long
Subdivision work complete. 2 SFHs in progress. DIs have inlet protection. No trackout, discharges, or uncontained trash observed. No corrections.
General Inspection8/14/20158/14/20158/14/2015 PASS
DetailsEvan Jenkins
Aging Inspection6/26/20156/26/20156/26/2015 PART
DetailsAndy J. Long
WIP on storm drain and irrigation infrastructure. No SFH work yet at Fairmont Square. Some trackout within site but not to Bogart or Caswell. No fugitive dust observed.

Did not see permit sign or NOI information. Will check with contractor. Subdivision was built mostly prior to being annexed by Boise in late 2014.
Complaint Inspection2/27/20152/27/20152/27/2015PPART
DetailsEvan Jenkins
Per ACHD: Dewatering is taking place, traveling through silt fence and down ditch. Extremely turbid water. Also, a site prep inspection was required, which was not called in
Contractor has 3 settling ponds set up that they are discharging into. Due to the high level of groundwater, pumped water doesn't have enough time of settle out before discharging into a ditch.
Correction:
1.) Set primary well point to draw down groundwater level
2.) Place 5 clean gravel check dams inside the ditch to slow velocity and aid sediment drop out.
Contractor began making changing immediately