As per ESC conditions, WUI Zone A, Class A roof, Permit for the construction of a new 3364 sq. ft., two story (first story 1934 sq. ft., second story 1430 sq. ft.) single family dwelling with 4 bedrooms, 4 bathrooms, approximately 235 sq. ft. of covered patio’s/porches and 1165 sq. ft. attached garage
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled10/19/201610/19/201610/19/2016PPASS
DetailsAndy J. Long
No further ESC inspections until Terra Nativa slide investigation and mitigation is complete. Alto Via Ct. is closed.
General Inspection10/19/201610/19/201610/19/2016 CANC
DetailsAndy J. Long
General Inspection10/4/201610/4/201610/4/2016 CANC
DetailsAndy J. Long
General Inspection9/19/20169/19/20169/19/2016 CANC
DetailsAndy J. Long
General Inspection9/2/20169/2/20169/2/2016 CANC
DetailsEvan Jenkins
area has been condemed
General Inspection8/18/20168/18/20168/18/2016 PEND
DetailsAndy J. Long
No inspection
General Inspection8/3/20168/3/20168/3/2016 CANC
DetailsAndy J. Long
Alto Via still under investigation and is closed
General Inspection7/19/20167/19/20167/19/2016 CANC
DetailsAndy J. Long
General Inspection7/4/20167/4/20167/4/2016 CANC
DetailsEvan Jenkins
holiday
General Inspection6/17/20166/17/20166/17/2016 CANC
DetailsAndy J. Long
General Inspection6/2/20166/2/20166/3/2016 CANC
DetailsEvan Jenkins
General Inspection5/18/20165/18/20165/18/2016 CANC
DetailsAndy J. Long
General Inspection5/3/20165/3/20165/3/2016 CANC
DetailsAndy J. Long
General Inspection4/18/20164/18/20164/18/2016 CANC
DetailsAndy J. Long
General Inspection4/1/20164/1/20164/1/2016 PASS
DetailsAndy J. Long
WIP on interior. No significant trackout. Front bank vegetation has been preserved and fiber wattle is installed at sidewalk. DI bag in MS4. No corrections at this time. Should be done by end of month
General Inspection3/17/20163/17/20163/17/2016 PASS
DetailsAndy J. Long
No trackout. No discharges. Trackout from last week was cleaned up and new rock installed on construction entrance. Front slope vegetation was preserved and perimeter wattle installed as well as DI sediment bag. Approved.
General Inspection3/2/20163/2/20163/4/2016 CANC
DetailsAndy J. Long
General Inspection2/16/20162/16/20162/16/2016 PASS
DetailsAndy J. Long
Tracking Control2/1/20162/1/20162/1/2016PPASS
DetailsAndy J. Long
Report of trackout and damage done to lots on Alto Via.

Inspected this site, the only active site on Alto Via and there are no violations.BMPs installed .

Trackout is no longer significant on street, but some cookies and mud bogging was done on an open stretch and trash and litter at the end of the culdesac. Appears to be the work of joy-riders...

General Inspection1/26/20161/26/20161/26/2016 PASS
DetailsAndy J. Long
General Inspection1/8/20161/11/20161/12/2016APASS
DetailsEvan Jenkins
General Inspection1/7/20161/7/20161/8/2016 CANC
DetailsAndy J. Long
rescheduled
General Inspection12/23/201512/23/201512/23/2015 CANC
DetailsAndy J. Long
Tracking Control11/27/201512/8/201512/10/2015APART
DetailsAndy J. Long
check track out

Trackout tracks into street cleaned. Some residual mud and dirt on sidewalk and gutter. Workers stayed off entrance today during the wet weather.

Need to conduct housekeeping and maintain DI bag as conditions dry out.
General Inspection11/27/201511/27/201511/27/2015 PART
DetailsBill VanDegrift
called rp about track out and left a message, set up reinspection
General Inspection11/12/201511/12/201511/12/2015 CANC
DetailsAndy J. Long
General Inspection10/28/201510/28/201510/28/2015 PASS
DetailsAndy J. Long
WIP. Road has been swept and construction entrance improved since last week's storm. No new corrections. RP-GC alerted ESC divisions of issues and corrections last week.
General Inspection10/12/201510/12/201510/12/2015APASS
DetailsAndy J. Long
WIP on initial phases of framing. Foundation is complete. No trackout or discharges coming from site. Edge of sidewalk and toe of front slope has fiber wattles installed properly for perimter sediment control and hillside vegetation has been preserved where possible. No corrections at this time.
General Inspection9/10/20159/10/20159/10/2015PPART
DetailsAndy J. Long
Project started without site preparation inspection. No permit sign posted.

Wattle installed at toe of slope and surrounding hillside vegetation has been preserved. No significant issues but Bruno Built needs to schedule site preparation inspections on all foothills homes.