Permit Information
Permit NumberESC15-01552
StatusFinaled
Name BOB GALLAGHER
Site Address 1257 W RIVER ST
Project Name13th & River Mixed Use Bld.
Customer Number 
ePlanReviewNo
Description
Construct a 4 story 16,581 sf mixed use office retail development with residential dormitory; Shell/Superstructure Only
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection12/23/201612/23/201612/28/2016 PASS
DetailsAndy J. Long
Construction complete. Parking lot, landscaping and stormwater facilites installed. No disturbed area, material stockpiles, or temporary BMPs remaining. ESC conditions satisfied.
DOC - Permit Finaled12/28/201612/28/201612/28/2016PPASS
DetailsAndy J. Long
General Inspection12/8/201612/8/201612/8/2016 CANC
DetailsAndy J. Long
General Inspection11/23/201611/23/201611/23/2016 PASS
DetailsAndy J. Long
WIP on interior. No exterior work. NO loose materials or discharges.
Site Final11/8/201611/8/201611/9/2016PNR
DetailsAndy J. Long
BLD permit for shell finaled. Some interior work remaining
Tracking Control11/8/201611/8/201611/8/2016PCANC
DetailsAndy J. Long
General Inspection11/7/201611/7/201611/8/2016 PASS
DetailsAndy J. Long
General Inspection10/21/201610/21/201610/21/2016 PASS
DetailsAndy J. Long
WIP on interior. Parking lot and drainage complete. No discharges or trackout.
General Inspection10/6/201610/6/201610/6/2016 PASS
DetailsAndy J. Long
WIP on interior. Exterior, parking lot paving and landscaping are installed and disturbed area stabilized. Interior work and ongoing equipment and material stagiing is occuring. No violations observed at time of inspection.
General Inspection9/21/20169/21/20169/21/2016 PASS
DetailsAndy J. Long
Final landscaping and site clean up in progress. Parking lot now paved, sidewalk median landscaped, and DI bag removed on corner. Should be ready for site final with BLD final.
General Inspection9/6/20169/6/20169/6/2016 PASS
DetailsAndy J. Long
General Inspection8/19/20168/19/20168/19/2016 PASS
DetailsEvan Jenkins
BMP Violation8/2/20168/3/20168/3/2016PPASS
DetailsAndy J. Long
Leaking washout area is now no longer leaking and the puddle and trackout is now swept up.

Initial response is good, need to remove the trash and dried concrete/stucco waste on Thursday and Friday.

No discharges or trackout
General Inspection8/2/20168/2/20168/2/2016 FAIL
DetailsAndy J. Long
Uncontained washout leaking and forming puddle at site entrance, and leading to trackout.

Need to clean up washout area immediately and prevent anymore washout there until puddle dries and can be cleaned up.

Verbal CN to begin clean up immediately and prohibit further washout activities in this uncontained puddle area.

Follow up inspection scheduled for tomorrow
General Inspection7/14/20167/14/20167/14/2016 PASS
DetailsEvan Jenkins
General Inspection6/28/20166/28/20166/28/2016PPASS
DetailsAndy J. Long
Vertical construction under way. ESC permit issued with foundation permit has been finaled. No trackout, storm drain has sediment protection. No fugitive dust or discharges observed. Approved.
General Inspection4/4/20164/4/20164/4/2016APASS
DetailsAndy J. Long
WIP on frame and apron to 13th street. Clean site with perimeter BMPs, inlet protection and permit sign posted on fence. No trackout or discharges. Gutters clean around both Visser sites on River. See also ESC15-02529 & ESC15-00942
Random Inspection3/7/20163/7/20163/7/2016PPASS
DetailsAndy J. Long
WIP. No trackout, construction entrance installed. MS4 on River has inlet bag protection. Clean site, good waste management and housekeeping.