Information based on query as of Tuesday, June 25, 2024.
Permit Information
Permit NumberESC16-00168
StatusFinaled
Name SAM F MCMILLEN
Site Address 8300 W VICTORY RD
Project NameRelocating 5 Mile Creek
Customer Number 
ePlanReviewNo
Description
Complete grading on the subject property to place fill and relocate 5-Mile Cr, as described in FEMA's Conditional Letter of Map Revision (CLOMR), Case No. 15-10-0997R, and dated November 4, 2015. These activities will "revise the effective Flood Insurance Study report and Flood Insurance Rate Map for" a portion of Boise City.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final4/5/20174/5/20174/5/2017PPASS
DetailsMelissa Jannusch
General Inspection4/5/20174/5/20174/5/2017 PASS
DetailsMelissa Jannusch
Project complete okay to final.
General Inspection3/21/20173/21/20173/21/2017 CANC
DetailsMelissa Jannusch
General Inspection3/6/20173/6/20173/7/2017 CANC
DetailsAndy J. Long
No activity at site. Wetland area relocation complete, will check for re-establishment next inspection. No issues reported at site.
General Inspection2/17/20172/17/20172/21/2017 PASS
DetailsMelissa Jannusch
General Inspection2/1/20172/1/20172/6/2017 CANC
DetailsAndy J. Long
General Inspection1/17/20171/17/20171/19/2017 CANC
DetailsAndy J. Long
General Inspection1/2/20171/2/20171/4/2017 CANC
DetailsAndy J. Long
General Inspection12/16/201612/16/201612/19/2016 CANC
DetailsAndy J. Long
General Inspection12/1/201612/1/201612/1/2016 CANC
DetailsAndy J. Long
General Inspection11/16/201611/16/201611/16/2016 CANC
DetailsAndy J. Long
General Inspection11/1/201611/1/201611/2/2016 CANC
DetailsAndy J. Long
General Inspection10/17/201610/17/201610/17/2016PPASS
DetailsAndy J. Long
No recent activity. Relocated wetland has had some vegetation fill in and area being used by ducks & geese. Large stockpile of rock and road mix still on site.

No violations, SWPPP and permit info located next to heavy duty rock construction entrance.
General Inspection10/13/201610/13/201610/13/2016 CANC
DetailsAndy J. Long
General Inspection9/28/20169/28/20169/28/2016 CANC
DetailsAndy J. Long
General Inspection9/1/20169/13/20169/12/2016PPASS
DetailsAndy J. Long
No new activity at site. Wetland vegetation still growing and irrigation water flowing through. SWPPP still posted at entrance. No trackout, fugitive dust, or materials leaving site.
General Inspection9/1/20169/1/20169/1/2016 CANC
DetailsAndy J. Long
rescheduled
General Inspection8/15/20168/15/20168/15/2016PPASS
DetailsAndy J. Long
Inspection or re-located wetland area. Wetlnad vegetation has started to grow within the designated mitigation area. Temporary irrigation water diversion lined channel has been removed. Water is flowing into the area and wate
control gates are complete.
Construction entrance and SWPPP info located on Victory.
General Inspection8/4/20168/4/20168/5/2016APASS
DetailsEvan Jenkins
Project is meeting BCC 8-17. No discharges leaving the site at time of inspection
Random Inspection6/27/20166/27/20166/27/2016PPASS
DetailsAndy J. Long
No construction actviity. No fugitive from graded area. Relocated wetland is in process of re-establishing.

No corrections issued at this time. Check for stabilization next inspection.
General Inspection5/4/20165/4/20165/4/2016PPASS
DetailsAndy J. Long
Grading and re-distribution of fill is on-going at site. No fugitive dust observed at time of inspection.

Rock construction entrance and permit sign are located at Victory Rd. No trackout from site.

Irrigation canal lining is installed and is allowing the ditch to travel through site without increasing sediment. Wetland material that was dredged has been stockpile to preserve seed and wetland soils. New wetland mitigation will include this material. Requested that site should check with wetlands specialist to see if stockpile should be kept moist.

No violations at site. Requested some minor maintenance on irrigation ditch lining at south property line.
General Inspection3/30/20164/7/20164/7/2016PPASS
DetailsAndy J. Long
Lining for irrigation ditch diversion channel is installed. The water flowing into the site is already quite turbid, but most like due to the initial flush of the system.

Construction entance preventing trackout, water truck on site for dust suppression.

No corrections requested at this time.
Site Preparation3/29/20163/30/20163/30/2016APASS
DetailsAndy J. Long
ESC & SWPPP sign posted. Rock construction entrance with geotextile lining is installed for site access off Victory.

Site is approved for 13.25 acres of disturbance, appropriate 404 permit has been approved to relocate the wetland area in the middle of the parcel to the northeast corner for mitigation. Wetland area is fed by Fivemile Creek (currently not flowing) which does convey irrigation water through site. A lined diversion ditch has been installed to diver the water flow around the wetland being filled, and eventually to the new wetland area.

Parcel owner and operator has CGPs filed (IDR12AD49 & IDR12AD62). Syman has prepared SWPPP and will help oversee initial BMP installment.

Soils from the graded area will be used to fill wetland area. The cut & fill is nearly balanced, so there will not be heavy truck traffic in and out of site.

Approved for construction. Will inspect next week to make sure diversion ditch is ready prior to irrigation water service starts for 2016.
General Inspection3/29/20163/29/20163/29/2016PCANC
DetailsAndy J. Long
Site prep scheduled for tomorrow 11 AM. Syman Co. on site installing BMPs...no inspection conducted at this time.