Permit Information
Permit NumberESC16-00973
StatusFinaled
Name JARON DOWALTER
Site Address 6772 W TARGEE ST
Project NameDillon RV grading/site improv.
Customer Number 
ePlanReviewNo
Description
Soil stripping top layer of vegetation, import earth fill material, new asphalt, curbing, landscaping and drainage swale. No new buildings. BMPs include sediment protection for drainage that leads to Threemile Creek as well as new swale, construction entrance trackout controls, protect MS4 inlet on Targee, fugitive dust control. Flat site in industrial area. ESC site preparation inspection is required, call 384-3802 or794-8996.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final3/12/20183/12/20183/12/2018PPASS
DetailsAndy J. Long
Construction complete. Temporary sediment bags on Targee installed from project have been removed. Completed permanent stormwater facilities retain stromwater on site, ESC permit conditions satisfied.
Site Final2/20/20182/21/20182/22/2018PCANC
DetailsAndy J. Long
General Inspection2/19/20182/19/20182/20/2018 CANC
DetailsAndy J. Long
General Inspection1/2/20181/2/20181/2/2018 CANC
DetailsAndy J. Long
General Inspection11/17/201711/17/201711/17/2017 CANC
DetailsAndy J. Long
Site Final10/2/201710/2/201710/2/2017PNR
DetailsAndy J. Long
some work still remains, no violations at site. No construction activity.
General Inspection9/22/20179/22/20179/22/2017 CANC
DetailsAndy J. Long
General Inspection8/7/20178/7/20178/7/2017 CANC
DetailsAndy J. Long
General Inspection6/21/20176/21/20176/21/2017 PASS
DetailsAndy J. Long
No construction activity. Some areas of the RV sale lot are in use. Permanent onsite stormwater facilities installed. PWK and GRD permits are open and SWPPP and COB ESC permit posted. Will continue to monitor. No ESC violations observed.
General Inspection5/2/20175/2/20175/2/2017 CANC
DetailsAndy J. Long
Site Final3/13/20173/14/20173/13/2017ANR
DetailsAndy J. Long
No violations at site. Perimeter landscaping on the north border not yet established. Parking lot paved and stormwater retention installed. Some stockpiles remain on site and minor activity. Will monitor through Spring
General Inspection3/8/20173/10/20173/13/2017ACANC
DetailsAndy J. Long
General Inspection3/8/20173/8/20173/8/2017 CANC
DetailsAndy J. Long
rescheduled for 3/10
General Inspection12/7/201612/14/201612/14/2016ACANC
DetailsAndy J. Long
General Inspection11/21/201612/6/201612/7/2016ACANC
DetailsAndy J. Long
rescheduled
General Inspection11/21/201611/21/201611/21/2016PPASS
DetailsAndy J. Long
WIP on new parking area. No trackout or discharges occuring. New onsite drainage has sediment protection. No corrections requested.
Site Preparation10/21/201610/24/201610/24/2016APASS
DetailsAndy J. Long
Jesse CA #: ###-####

Onsite meeting with RP Jaron and K2 super-indentant Ty.

Industrial/commercial site with onsite retention. Project duration is < 2 months. DI bag installed to the west of existing stabilized entrance on Targee. Silt fence installed on north boundary to protect drainage/irrigation ditch parallet to I-84. Requested that water truck be available for fugitive dust control as needed. Currently okay w/o. Site has SWPPP for CGP.

Approved for construction. Grading now in progress.