Permit Information
Permit NumberESC16-01593
StatusFinaled
Name CLAYTON BROOKS
Site Address 4450 E PARKCENTER BLVD
Project NameHarris Ranch Community Center
Customer Number 
ePlanReviewNo
Description
Community swimming pool with changing rooms and mailbox room. Note: project is on Millbrook in DHE#14. SWPPP narrative and site map submitted. eNOI filed IDR12B022. ESC BMPs include stabilized construction entrance, concrete washout containment, and sediment protection along Warms Springs Creek. Site preparation inspection required prior to earth work, call 608-7070 to schedule.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection11/17/201711/17/201711/20/2017 CANC
DetailsMichael Zawacki
DOC - Permit Finaled11/20/201711/20/201711/20/2017PPASS
DetailsMichael Zawacki
General Inspection11/2/201711/2/201711/3/2017PPART
DetailsAndy J. Long
Need to clean up wind blown trash in Warm Springs Creek adjacent to project...email sent to Noah with RCH.

Almost ready for final after final cleanup
Random Inspection10/19/201710/19/201710/19/2017PPASS
DetailsMichael Zawacki
landscaping complete. Site clean, interior work in progress.
General Inspection10/11/201710/11/201710/12/2017 PASS
DetailsAndy J. Long
General Inspection9/26/20179/26/20179/28/2017 CANC
DetailsAndy J. Long
General Inspection9/8/20179/8/20179/8/2017 CANC
DetailsAndy J. Long
General Inspection8/24/20178/24/20178/24/2017 PASS
DetailsAndy J. Long
No trackout or discharges. Silt fence BMP in good condition. Approved
General Inspection8/9/20178/9/20178/10/2017 CANC
DetailsAndy J. Long
General Inspection6/8/20176/8/20176/8/2017PPASS
DetailsMelissa Jannusch
WIP. Trash is contained. No trackout. Property is now fenced. No corrections.
General Inspection5/30/20175/30/20175/30/2017PPASS
DetailsAndy J. Long
Permit sign posted. Road and gutter in front of site are free of trackout & loose sediment. Silt fence installed between project and Warm Spring Creek (now dry). Approved.
BMP Violation5/12/20175/17/20175/17/2017PPASS
DetailsMelissa Jannusch
Concrete washout installed, trash containment set up.
General Inspection5/12/20175/12/20175/12/2017PFAIL
DetailsMelissa Jannusch
Started without site preparation inspection. No concrete washout. No trash containment. Called RP requesting that he schedule site preparation inspection in the future, have concrete washout on site, and contain trash. Silt fence is ok. Follow up scheduled for Wednesday.