Permit Information
Permit NumberESC17-01088
StatusFinaled
Name NICHOLE RUWE
Site Address 2501 S CLOVERDALE RD
Project NameGraywoods Estates
Customer Number 
ePlanReviewNo
Description
Subdivision site slopes to the NE, install fiber rolls along Cloverdale. Plan notes state that perimeter swales are to be built prior to construction to retain stormwater onsite. Stabilized construction entrance.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final4/20/20204/21/20204/23/2020PPASS
DetailsAndy J. Long
SWPPP sign removed as requested and broken sandbags cleaned up. DI bags left in drain for the 2-3 remaining open lots to be under construction

ESC permit finaled.
General Inspection4/20/20204/20/20204/20/2020 CANC
DetailsAndy J. Long
Site Final3/4/20203/5/20203/5/2020ANR
DetailsAndy J. Long
Notified developer to remove:

- old wooden sign board
- broken sandbags around storm drains
- temporary DI bags

CGP is also still "active" for the sub. Only 2 lots left. No active construction.
General Inspection3/3/20203/3/20203/4/2020 PASS
DetailsAndy J. Long
No activity. 2 open lots remain. No active construction. Storm drains have sediment protection still installed. Going to request to developer to remove sign and storm drain bags
General Inspection1/17/20201/17/20201/17/2020 CANC
DetailsMichael Zawacki
General Inspection12/2/201912/2/201912/2/2019 CANC
DetailsAndy J. Long
General Inspection10/15/201910/15/201910/15/2019 PASS
DetailsMichael Zawacki
WIp on a few homes in back. No trackout or blowing dust. No issues at time of inspection. ite still has some vacant lots.
General Inspection8/30/20198/30/20198/30/2019 CANC
DetailsAndy J. Long
General Inspection7/15/20197/15/20197/15/2019PPASS
DetailsMichael Zawacki
No issues at site.
General Inspection6/6/20196/6/20196/6/2019PFAIL
DetailsMichael Zawacki
Neighborhood is mess. Talked to workers on site and sent message to rp for homes with no one on site.
Lots of dirt on roads and trash laying around.
General Inspection5/8/20195/9/20195/9/2019PPART
DetailsMichael Zawacki
Lots of building waste around site. Sod piles laying around site, lots of dirt coming off back building lots.
Conference4/3/20194/10/20194/18/2019ACANC
DetailsMichael Zawacki
Tracking Control3/29/20194/3/20194/3/2019AFAIL
DetailsMichael Zawacki
Majority of issues are on rear of site. Workers turning around in mud, lots of loose trash, concrete washout is overflowing. Conference with all responsible persons needed.
BMP Violation3/26/20193/29/20193/29/2019AFAIL
DetailsMichael Zawacki
Trackout throughout site.
Tracking Control3/29/20193/29/20193/29/2019PFAIL
DetailsMichael Zawacki
BMP Violation3/22/20193/26/20193/26/2019AFAIL
DetailsMichael Zawacki
Lots of trackout, all coming from 2695 Simsbury, does not have ESC permit. Talked to owner, told him he needed to clean road since his cabinent delivery is the only person driving in mud.
BMP Violation3/20/20193/22/20193/22/2019APEND
DetailsMichael Zawacki
Cleanup not done at time of inspection. Talked to foreman on site, will clean later in day. Follow up scheduled for next week.
General Inspection3/20/20193/20/20193/20/2019PFAIL
DetailsMichael Zawacki
Dumped washout has never been cleaned, one lot has a washout and it is full. Lots of dirt on roads and sidewalks. Lots of building waste and wind blown trash all over site.
3 builders working on site.
Conference3/6/20193/7/20193/7/2019PDONE
DetailsAndy J. Long
Chad will have HOA landscapers maintain DI bags. Todd Christensen (4 lots) will provide ecopan washout for projects. Other builders to have their own washouts.

Notified them of CGP requirements for NOI and following swppp. SFHs to be permitted seperately.
BMP Violation2/8/20192/13/20192/15/2019APEND
DetailsAndy J. Long
check on washout and DI bag maintenance request

Developer Chad has arranged to have DI bags maintained. Stated he has notified all builders about the washout violations
BMP Violation2/8/20192/8/20192/8/2019AFAIL
DetailsAndy J. Long
No designated & lined washout. DI bags full. Listed RP on CGP sign no longer associated with project.

Corrections:
- developer to notify all builders about concrete washout policy. May get a designated washout and split cost.
- clean out DI bags at subdivision entrance. Replace and/or maintain at a minimum of once monthly.

Verbal corrections issued to developer Chad ###-####
General Inspection1/17/20191/17/20191/17/2019PPART
DetailsMichael Zawacki
All home construction is framing. Site is mostly clean, one person has driven through mud and tracked dirt.
General Inspection12/17/201812/17/201812/18/2018PPASS
DetailsAndy J. Long
DI bags installed. WIP on 3 SFHs. No significant trackout, no discharges
Tracking Control11/2/201811/6/201811/8/2018PFAIL
DetailsMichael Zawacki
No cleanup of trackout or BMPs installed at remodel. Crew starting to install forms for new home, no washout pit dug or pan on site. Lots of small trash blown all over site.
General Inspection10/29/201810/29/201810/29/2018PPASS
DetailsAndy J. Long
Storm drains have sediment filter bags installed. New homes now in progress. Some trackout within subdivision from one of homesites No issues along perimeter of Cloverdale.

General Inspection10/12/201810/12/201810/12/2018 FAIL
DetailsMichael Zawacki
Lots of trackout into street. Majority caused by the existing brick house, trees have been cut down and looks like they drove through the mud to do it.
General Inspection8/27/20188/27/20188/27/2018PPASS
DetailsMichael Zawacki
Two homes now under construction, both have permits. No ESC issues at site.
General Inspection7/10/20187/10/20187/10/2018PPASS
DetailsAndy J. Long
WIP on installing subdivsion irrigation and common area landscaping. No trackout or discharges from subdivision. No fugitive dust observed. Approved.
General Inspection6/5/20186/5/20186/5/2018PPASS
DetailsMichael Zawacki
No new activity. No erosion issues from rain events.
General Inspection4/30/20185/15/20185/16/2018APASS
DetailsMichael Zawacki
No new activity.
Random Inspection5/7/20185/7/20185/7/2018PPASS
DetailsMichael Zawacki
Site is inactive, no changes since last inspection. Syman is doing monthly SWPPP inspections. One stockpile on site. Access to Cloverdale has been closed, must access through neighborhood.
General Inspection4/30/20184/30/20184/30/2018PPASS
DetailsAndy J. Long
Roads are now paved. Grading complete. New storm drains have sediment bags installed. No loose trash or stockpiles left behind.Will need to vegetate/stabilize to prevent dust issue.
General Inspection4/4/20184/4/20184/4/2018PPASS
DetailsMichael Zawacki
Sidewalks and entrance off of Cloverdale now complete. Road inside development also completed. Site is currently idle.
General Inspection2/27/20183/8/20183/12/2018PPASS
DetailsAndy J. Long
WIP to complete paving. No trackout or sediment runoff to Cloverdale. No fugitive dust observed
General Inspection2/21/20182/28/20182/27/2018PCANC
DetailsAndy J. Long
General Inspection2/21/20182/21/20182/21/2018PPASS
DetailsAndy J. Long
Road prepped for paving and curb and gutter. No trackout. WIP on sidewalk along Cloverdale. Trech dug between area and road shoulder, no sediment leaving site. Will check back in two weeks for stockpile stabilization. No requests issued.
Random Inspection1/30/20181/30/20181/30/2018PPASS
DetailsMichael Zawacki
WIP, grader on site working on road bed. No dust leaving site. No trackout onto Cloverdale or cul-de-sac. Sweeper is parked on site by enterance.
General Inspection1/2/20181/2/20181/2/2018APASS
DetailsAndy J. Long
No activity. Road has been graded but still needs utilities and paving. Multiple stockpiles on site, some bermed up along Cloverdale. No trackout, SWPPP posted on Simsbury.
Tracking Control11/24/201711/27/201711/27/2017AFAIL
DetailsMichael Zawacki
Trackout onto S Simsbury Place. No entrance constructed. Called listed RP and left message.
Complaint Inspection11/22/201711/22/201711/24/2017PPEND
DetailsAndy J. Long
extreme trackout reported.
General Inspection10/2/201710/12/201710/16/2017PPASS
DetailsMichael Zawacki
No WIP. Entire site has been tracked. Perimeter BMPs intact. Lots of trackout, called RP listed on permit to come get someone to clean up.
Random Inspection10/2/201710/2/201710/2/2017PPASS
DetailsAndy J. Long
No activity. No trackout or discharges from site. Permit sign posted.
Site Preparation9/15/20179/15/20179/15/2017APEND
DetailsAndy J. Long
Site rough grading is in progress. Pre-construction meeting already completed.

Water truck and construction entrance rock are onsite. SWPPP is being revised by JEC.

RP with Knife River not onsite

Verbal request to crew to use water truck simultaneously with grading. Agreed and got in water truck.

Will check back. NO trackout, perimeter vegetative buffer has been preserved.