Site Final | 6/16/2020 | 6/16/2020 | 6/18/2020 | P | PASS |
Andy J. Long
|
|
|
Temp BMPs removed. Site clean and stabilized. Approved
|
General Inspection | 6/16/2020 | 6/16/2020 | 6/16/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/29/2020 | 4/29/2020 | 4/29/2020 | | PASS |
Michael Zawacki
|
|
|
Parking lot paved, curbing and sidewalks completed. None of the grass areas have been landscaped. No issues.
|
General Inspection | 3/9/2020 | 3/9/2020 | 3/10/2020 | P | PASS |
Michael Zawacki
|
|
|
Met with foreman on site. Discovered two more old drains to canal, steel plate and cement to seal them. Masons on site doing brick at bottom of walls. Some uncontained washout from stucco, will get it clean. Has trash cleanup coming in to walk and clean site.
|
General Inspection | 2/24/2020 | 2/24/2020 | 2/24/2020 | P | PART |
Michael Zawacki
|
|
|
No trackout from entrance. Lotsd of loose debris at site, cardboard, styrofoam, etc. All fenced in, nothing blowing off site.
|
General Inspection | 12/5/2019 | 12/5/2019 | 12/6/2019 | P | PASS |
Michael Zawacki
|
|
|
Trucks on site hauling at backfill, no trackout on overland at time of inspection. Crews on site installing vapor barrier and bar on inside of foundation, walls already poured. Washout on site but currently not accesible. Lots of trash on site, all in piles. Area is fenced in so garbage can't blow away. Site is below grade.
|
General Inspection | 10/22/2019 | 11/6/2019 | 11/6/2019 | P | PASS |
Andy J. Long
|
|
|
WIP on preparing foundation. Concrete washout pan on site. No trackout or fugitive dust.
Noticed an unprotected storm drain near the gararge structure. Requested that it have sediment protection.
|
Site Preparation | 10/21/2019 | 10/22/2019 | 10/22/2019 | A | PASS |
Andy J. Long
|
|
|
mIKE Phone #: ###-####
Building on site has been demolished and hole filled in with pit run. RP states that existing asphalt around the pit run area will be preserved other than any trenching for utilities that may be required.
Will need to have concrete washout pan, spill kit, and other pollution control measures. Drainage appears to stay onsite draining to the NE corner of parcel. Construction has not yet started.
|