General Inspection | 8/10/2020 | 8/10/2020 | 8/10/2020 | P | PASS |
Andy J. Long
|
|
|
WIP. NO trackout or loose dirt around perimeter. Trash contained. Water line or utility cuty on back slope behind home, will need stabilization and/or perimeter sediment control
|
General Inspection | 7/22/2020 | 7/22/2020 | 7/22/2020 | P | PASS |
Michael Zawacki
|
|
|
WIP on framing, site is clean.
|
General Inspection | 6/1/2020 | 6/1/2020 | 6/1/2020 | P | PASS |
Michael Zawacki
|
|
|
Site clean. Pour is scheduled for today, site has lined washout.
|
General Inspection | 5/28/2020 | 5/28/2020 | 5/28/2020 | P | PASS |
Michael Zawacki
|
|
|
Building pad has been excavated. Crew has started setting forms, no workers at site. Site still needs washout.
|
General Inspection | 5/14/2020 | 5/14/2020 | 5/15/2020 | P | CANC |
Michael Zawacki
|
|
|
|
Site Preparation | 5/14/2020 | 5/14/2020 | 5/14/2020 | P | PASS |
Andy J. Long
|
|
|
WIP. Vegetative buffer preserved below site. Will need to keep sidewalk and gutter clean at all times.
No trackout or muddy runoff from site observed during rain
|