Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR00-00204
StatusFinaled
Name TREASURE VALLEY FIRE
Site Address 255 N STEELHEAD WAY
Project NameSPR SCP GLOBAL TECH
Customer Number 
ePlanReview 
Description
To fire sprinkler an 18,357 sq. ft. area within an existing 54,824 sq.ft. structure for use as an "H6 / H7" semiconductor facility with office and storage ancillary areas per approved plans on file. Work to include modification of sprinkler for construction of interior, non-bearing, noncombustible framing, to create 1 & 2-hour occupancy separations around the "H6/H7" Fab Area from adjoining uses and to create a 1-hour exit corridor system to serve as required exits from the areas. All work to be per UFC, NFPA (related) and Boise Fire Department requirements. NOTE: This building is fully fire sprinklered for allowable area increase. BLD99-0360 *JWA*
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/8/20021/8/20021/8/2002APASS
DetailsTroy Cobbley
Added by Inspector: 430 On 1/8/2002 10:59:48 AM finaled by 406
INSP-Final Inspection10/31/200010/31/200010/31/2000PPART
DetailsJoe Tawney
Rick ###-#### pager OK on spklr system for project 11/1/2000 7:55:30 AM
INSP-Sprinkler Rough-in/Hydro10/9/200010/9/200010/9/2000PPART
DetailsJoe Tawney
rick pager ###-#### OK on hydro tesr for
clean room 10/10/2000 7:56:56 AM
INSP-Sprinkler Rough-in9/26/20009/26/20009/26/2000PPART
DetailsJoe Tawney
r/i rick --pager ###-#### OK on rough in of office area and corridors 9/27/2000 8:09:31 AM
INSP-Sprinkler Rough-in9/25/20009/25/20009/25/2000PPART
DetailsJoe Tawney
rick-- ###-#### value installation insp OK on installation of PIV valve 9/26/2000 7:28:00 AM
INSP-Sprinkler Rough-in9/21/20009/21/20009/21/2000PPART
DetailsJoe Tawney
r/i-- pager ###-#### -rick OK on rough in of cleanroom and subfloor 9/22/2000 7:59:43 AM
INSP-Conference7/6/20007/7/20007/7/2000APART
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 07/06/2000 at 12:01:06. Contact: ###-####. Ok to cover hard lid in corridors ok to install ceiling in cleanroom. 7/7/00 1:39:47 PM