INSP-Final Inspection | 8/14/2001 | 8/14/2001 | 8/14/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 8/14/2001 4:37:19 PM
|
INSP-Final Inspection | 12/7/2000 | 12/7/2000 | 12/7/2000 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 12/7/2000 2:45:11 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/25/2000 | 10/25/2000 | 10/25/2000 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/25/2000 at 07:22:48. Contact: ###-####.hydro okay - nned to test FDC; r/i need straps on all hangers, replace heads on anti-freeze loop, sign for FDC indicating gymnasium only, 10/26/2000 12:00:15 PM
|
INSP-Supply line flush | 10/23/2000 | 10/23/2000 | 10/23/2000 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/23/2000 at 08:37:53. Contact: ###-####. underground flush okay 10/24/2000 8:00:15 AM
|
INSP-Conference | 8/18/2000 | 8/18/2000 | 8/18/2000 | A | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 8/18/2000 sprinkler plans not approved - told contractor to get Shilo plans resubmitted for approval. system is installed except for the riser.
|