INSP-Final Inspection | 8/14/2001 | 8/14/2001 | 8/14/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 8/14/2001 4:30:26 PM
|
INSP-Final Inspection | 3/27/2001 | 3/30/2001 | 3/30/2001 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/27/2001 at 16:46:32. Contact: ###-####.
|
INSP-Supply line flush | 2/23/2001 | 2/23/2001 | 2/23/2001 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 02/23/2001 at 08:22:23. Contact: ###-####. hydro test okay on underground 2/23/2001 10:50:11 AM
|
INSP-Sprinkler Rough-in/Hydro | 2/21/2001 | 2/21/2001 | 2/21/2001 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 02/21/2001 at 09:32:15. Contact: ###-####. hydro test okay for overhead of both dry and wet systems; still need to hydro the underground 2/21/2001 5:27:17 PM
|
INSP-Sprinkler Rough-in | 12/6/2000 | 12/6/2000 | 12/6/2000 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 12/6/2000 4:00:51 PM ///// heads overspaced in cathedral area; sprinklers required under stage; dry plans not on-site; insulation covering wet pipe 12/6/2000 4:03:13 PM
|
INSP-Supply line flush | 12/4/2000 | 12/5/2000 | 12/6/2000 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/04/2000 at 15:40:04. Contact: ###-####.////flush already complete 12/6/2000 4:01:36 PM
|
INSP-Supply line flush | 12/1/2000 | 12/4/2000 | 12/4/2000 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/01/2000 at 11:43:32. Contact: ###-####.////// underground flush okay 12/4/2000 3:10:25 PM
|