Permit Information
Permit NumberFIR00-00627
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 3639 S FEDERAL WAY
Project NameSPR HOME DEPOT
Customer Number 
ePlanReview 
Description
THE HOME DEPOT * TO INSTALL A FIRE SPRINKLER SYSTEM PER NFPA 13, 231C, 24, 72 AND UFC GUIDELINES IN A NEW 115,405 SQ. FT., ONE STORY, HOME IMPROVEMENT RETAIL SALES BUILDING WITH ADJOINING 20,125 SQ. FT. GARDEN CENTER AND RELATED WORK. THIS BUILDING IS CONSTRUCTED OF EXTERIOR MASONRY WALLS WITH STEEL STRUCTURAL FRAME AND METAL ROOF SYSTEM. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST THIS BUILDING IS TO BE FULLY FIRE SPRINKLERED. THE SPRINKLERS ARE USED FOR UNLIMITED AREA. BUILDING PERMIT: BLD00-01783. DRH00-00099, CUP00-00040. *JWA*
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/14/20015/14/20015/14/2001PPASS
DetailsRick Jackson
Added by Inspector: 409 On 5/14/2001 3:29:48 PM
INSP-Final Inspection5/4/20015/7/20015/7/2001APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 05/04/2001 at 09:40:50. Contact: ###-####. dry system test at 59 seconds; need to test alarms 5/7/2001 11:13:13 AM
INSP-Final Inspection5/3/20015/3/20015/3/2001PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 05/03/2001 at 08:41:54. Contact: ###-####. okay on aerosol racking 5/3/2001 2:49:07 PM
INSP-Final Inspection4/26/20014/27/20014/27/2001PCANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 04/26/2001 at 12:38:05. Contact: ###-####.
INSP-Final Inspection4/9/20014/11/20014/11/2001PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 04/09/2001 at 15:26:19. Contact: ###-####. dry sprinkler system took 72 seconds; inspector test in wrong location 4/11/2001 6:12:17 PM
INSP-Sprinkler Rough-in/Hydro3/14/20013/15/20013/15/2001APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 03/14/2001 at 15:22:22. Contact: ###-####. hydro on all wet systems okay 3/15/2001 1:16:21 PM
INSP-Sprinkler Rough-in/Hydro3/13/20013/14/20013/14/2001AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 03/13/2001 at 08:31:16. Contact: ###-####. c/n issued 3/14/2001 11:33:06 AM
INSP-Sprinkler Rough-in/Hydro2/19/20012/20/20012/20/2001AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 02/19/2001 at 08:30:50. Contact: ###-####. c/n issued - earthquaking; FDC location; clearance at base of riser; dry and rack systems not approved 2/21/2001 10:33:44 AM