INSP-Final Inspection | 4/26/2001 | 4/26/2001 | 4/26/2001 | P | NR |
Joe Tawney
|
|
|
becky ###-#### Not ready for inspection 4/26/2001 5:48:45 PM
|
INSP-Sprinkler Rough-in/Hydro | 4/26/2001 | 4/26/2001 | 4/26/2001 | P | PASS |
Joe Tawney
|
|
|
above ground hydro test becky ###-#### OK on spklr rough in 4/26/2001 5:48:05 PM
|
INSP-Final Inspection | 4/16/2001 | 4/17/2001 | 4/17/2001 | P | NR |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 04/16/2001 at 17:05:57. Contact: ###-####.
|
INSP-Sprinkler Rough-in/Hydro | 4/17/2001 | 4/17/2001 | 4/17/2001 | P | PASS |
Joe Tawney
|
|
|
Added by Inspector: 406 On 4/17/2001 3:08:36 PM OK on above ground hydro test
|
INSP-Sprinkler Rough-in/Hydro | 4/16/2001 | 4/17/2001 | 4/17/2001 | P | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 04/16/2001 at 17:05:19. Contact: ###-####. Fail Spklr rough in. 4/17/2001 3:07:32 PM
|