INSP-Final Inspection | 11/19/2001 | 11/20/2001 | 11/20/2001 | A | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 11/19/2001 5:24:18 PM
|
INSP-Final Inspection | 11/16/2001 | 11/19/2001 | 11/19/2001 | P | FAIL |
Rick Jackson
|
|
|
###-#### DAVE X2 bell shut-off problems; preaction not ready 11/19/2001 5:23:55 PM
|
INSP-Sprinkler Rough-in/Hydro | 11/1/2001 | 11/2/2001 | 11/2/2001 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/01/2001 at 09:51:53. Contact: ###-####. hydro on cafeteria only okay. 11/2/2001 9:59:32 AM
|
INSP-Sprinkler Rough-in/Hydro | 10/26/2001 | 10/29/2001 | 10/29/2001 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/26/2001 at 12:01:05. Contact: ###-####. fireproofing on heads; EQ'ing not completed; need hydro test still 10/29/2001 3:00:50 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/25/2001 | 10/26/2001 | 10/26/2001 | P | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/25/2001 at 08:52:14. Contact: ###-####. received a call from Mike and they will reschedule for 10/29 10/26/2001 11:55:17 AM
|
FIR-Aging Inspection | 6/19/2001 | 6/19/2001 | 6/19/2001 | | NR |
Rick Jackson
|
|
|
work still under progress 6/19/2001 10:37:31 AM
|