Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR01-00011
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 8000 FEDERAL WAY
Project NameSPR MIC #36-OFFICE
Customer Number 
ePlanReviewNo
Description
MICRON BUILDING #36 TWO STORY OFFICE SECTIONS B, C & D T. I. (PCS 36-20003157) TO FIRE SPRINKLER THE TENANT IMPROVEMENT FOR OCCUPANCY. THIS IS A 216,000 FT/2, TWO STORY OFFICE BUILDING WITH A 2100 SQ. FT. BASEMENT BUILDING THAT WILL CONTAIN OFFICES, CONFERENCE ROOMS, I. S. MACHINE ROOM, LOGISTICS & COMP. LAB, MAL LAB, SIGNAL INTEGRITY/MODULE LAB, TESTERS, ASRL LAB AND UPS AND BATTERY ROOMS AT THE BASEMENT. THIS T. I. IS BEING DONE WITHIN A NEW SHELL BUILDING CONSTRUCTED UNDER PERMIT BLD00-01726. ALL INSTALLATION WORK SHALL BE PER THE APPROVED PLANS, ATTACHED COMMENT LIST, UFC, RELATED/ADOPTED NFPA PAMPHLETS, BCO AND FIRE DEPARTMENT REQUIREMENTS. THIS BUILDING IS DIVIDED BY TWO, TWO-HOUR AREA SEPARATION WALLS. THIS BUILDING REQUIRES FULL FIRE SPRINKLER PROTECTION FOR AREA INCREASE. *JWA*
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/20/200111/20/200111/20/2001PPASS
DetailsRick Jackson
Added by Inspector: 409 On 11/20/2001 7:28:23 PM
INSP-Sprinkler Rough-in/Hydro10/12/200110/15/200110/15/2001PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/12/2001 at 11:07:36. Contact: ###-####. pre-action hydro okay; all items from previous inspection corrected; areas 1-2 (cafeteria) not completed. 10/15/2001 2:27:11 PM
INSP-Sprinkler Rough-in/Hydro10/3/200110/4/200110/4/2001PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/03/2001 at 15:26:21. Contact: ###-####. hydro on all systems except 1-2 and preaction completed; need EQ on basement main 10/4/2001 3:39:11 PM
INSP-Sprinkler Rough-in9/24/20019/25/20019/25/2001AFAIL
DetailsRick Jackson
Scheduled by Inspector: 409 On 9/24/2001 2:50:52 PM around 10 am EQ's see FP sheets for areas 3-4-5-6 on first floor 9/25/2001 11:34:22 AM
INSP-Sprinkler Rough-in/Hydro9/21/20019/24/20019/24/2001PNR
DetailsRick Jackson
Scheduled by a contractor via Hello! on 09/21/2001 at 09:05:22. Contact: ###-####.
INSP-Sprinkler Rough-in/Hydro9/19/20019/21/20019/21/2001ACANC
DetailsJoe Tawney
Cancel To be rescheduled to 9/24/01 9/21/2001 9:08:40 AM
INSP-Sprinkler Rough-in9/13/20019/14/20019/14/2001AFAIL
DetailsRick Jackson
r/i- forest- ###-#### need EQ between area5-6 on 2nd floor; need EQ at stair in area 4. 9/14/2001 10:40:36 AM
INSP-Sprinkler Rough-in7/24/20017/25/20017/25/2001APART
DetailsRick Jackson
forest ###-#### area 7 and 8 first floor okay; area 7 and 8 second floor require earthquake on 4 inch south side and at 2 hour wall east side. will verify the spacing in soffit in area 8 7/25/2001 3:44:39 PM
INSP-Supply line flush6/28/20016/28/20016/28/2001PPART
DetailsRick Jackson
Added by Inspector: 409 On 6/28/2001 3:22:31 PM underground flush only okay
FIR-Aging Inspection6/19/20016/19/20016/19/2001 NR
DetailsRick Jackson
work still under progress 6/19/2001 10:37:20 AM