Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR01-00098
StatusFinaled
Name TREASURE VALLEY FIRE
Site Address 6140 W CURTISIAN AVE
Project NameSPR ST ALPHONSUS (BLDG #6)
Customer Number 
ePlanReview 
Description
SAINT ALPHONSUS MEDICAL OFFICE BUILDING #6 SHELL AND CORE * TO INSTALL A COMPLETE FIRE SPRINKLER SYSTEM IN A NEW 60,350 FT/2, (15,665 FT/2. BASEMENT), FOUR STORY SHELL & CORE MEDICAL OFFICE BUILDING INCLUDING RELATED 6" C-900 FIRE SPRINKLER UNDERGROUND MAIN SUPPLY LINE. THIS BUILDING IS CONSTRUCTED OF STEEL STRUCTURAL FRAME, CONCRETE PAN DECK FLOORS, METAL ROOF DECK, METAL EXTERIOR NONBEARING STUD WALLS AND MASONRY STAIR ENCLOSURES. THE PERMIT ALSO INCLUDES THE PROTECTION OF A 155 LINEAL FOOT BY 14 FOOT WIDE NONCOMBUSTIBLE ELEVATED PEDESTRIAN WALKWAY LINK FROM THE SOUTHEAST CORNER OF THE THIRD FLOOR OF BUILDING #6 TO THE NORTHWEST CORNER OF THE EXISTING NORTH TOWER OFFICE BUILDING TO THE SOUTH. ALL FIRE SPRINKLER AND RELATED WORK PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. THIS IS SHELL AND CORE SPRINKLER PERMIT ONLY, SEPARATE TENANT IMPROVEMENT SPRINKLER PERMITS WILL BE REQUIRED TO FINISH THIS BUILDING FOR OCCUPANCY. THIS BUILDING REQUIRES TO BE FULLY FIRE SPRINKLERED. DUP98-00142/DRH98-00196/PC#474-00 GRADING: BLD98-03934, BUILDING PERMIT: BLD00-01744. *JWA*
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/24/20021/24/20021/24/2002PFAIL
DetailsTroy Cobbley
Added by Inspector: 430 On 1/24/2002 7:45:28 PM provide spare heads in head box with wrench, provide caps and chains on hose valves, provide sprinkler canopies at the top of the south stairs, provide flexible coupling on 3" riser in penthouse, replace clappers in backflow preventer, verify that the 2nd, 3rd and 4th floors flow switches meet the 90 second rule, verify sprinkler at the top of the north shaft, install heat collector at the bottom of the north shaft above head, time main flow switch, send supervisory and trouble signals from the main riser room
INSP-Sprinkler Rough-in/Hydro1/9/20021/9/20021/9/2002PPART
DetailsTroy Cobbley
Added by Inspector: 430 On 1/9/2002 2:13:57 PM Basement, 1st, 2nd, 3rd and 4th floor sprinkler rough-in OK. Riser room, stand pipes, floor control valving, elevator shafts and finished lobby areas have not been reviewed
INSP-Sprinkler Rough-in7/31/20018/1/20018/1/2001APART
DetailsJoe Tawney
###-#### OK on spklr rough in exc for 3rd flr link which has not been constructed 8/1/2001 10:07:25 AM
INSP-Sprinkler Rough-in/Hydro7/31/20017/31/20017/31/2001PPART
DetailsJoe Tawney
###-#### Ok on hydro test exc for 3rd flr link which has not been constructed 8/1/2001 10:06:28 AM
INSP-Supply line flush5/2/20015/3/20015/3/2001APART
DetailsJoe Tawney
. 5/3/2001 11:44:38 AM OK on underground hydro test and OK on supply line flush 5/3/2001 11:45:14 AM
INSP-Sprinkler Rough-in/Hydro3/28/20013/29/20013/29/2001PNR
DetailsJoe Tawney
Sam ###-#### Not ready to be rescheduled 3/30/2001 8:50:05 AM
INSP-Sprinkler Rough-in/Hydro3/27/20013/28/20013/28/2001ACANC
DetailsJoe Tawney
###-####--cancel per sam
INSP-Sprinkler Rough-in/Hydro3/28/20013/28/20013/28/2001PNR
DetailsJoe Tawney
Not ready to be rescheduled 3/29/2001 8:06:16 AM
INSP-Sprinkler Rough-in3/21/20013/22/20013/22/2001APART
DetailsJoe Tawney
OK to cover suppl line 3/22/2001 12:52:56 PM