INSP-Sprinkler Rough-in/Hydro | 7/2/2001 | 7/2/2001 | 7/2/2001 | P | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 07/02/2001 at 11:26:11. Contact: ###-####.-- -wrong permit #
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2001 | 7/2/2001 | 7/2/2001 | P | PART |
Joe Tawney
|
|
|
Spklr rough in Finish EQ bracing of risers, Add 1 head is storage area, Address beam obstruction in storage area 7/2/2001 4:53:44 PM
|
INSP-Supply line flush | 6/8/2001 | 6/8/2001 | 6/8/2001 | P | PART |
Joe Tawney
|
|
|
OK on supply line flush 6/8/2001 1:39:32 PM
|
INSP-Supply line flush | 6/6/2001 | 6/7/2001 | 6/7/2001 | P | CANC |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 06/06/2001 at 08:17:46. Contact: ###-####.----cancel per shilo
|
INSP-Supply line flush | 6/6/2001 | 6/7/2001 | 6/7/2001 | P | CANC |
Joe Tawney
|
|
|
Cancel water not turned yet 6/7/2001 2:10:43 PM
|
INSP-Supply line flush | 4/25/2001 | 4/25/2001 | 4/25/2001 | P | PASS |
Joe Tawney
|
|
|
4/26/2001 8:56:24 AM OK to cover spklr supply line 4/26/2001 8:56:42 AM
|
INSP-Supply line flush | 4/23/2001 | 4/23/2001 | 4/23/2001 | P | CANC |
Joe Tawney
|
|
|
Cancel To be rescheduled 4/23/2001 1:29:17 PM
|
INSP-Supply line flush | 4/19/2001 | 4/20/2001 | 4/20/2001 | A | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 04/19/2001 at 14:55:55. Contact: ###-####. OK on supply line stub in to bldg 4/20/2001 11:55:20 AM
|