*STEIN DISTRIBUTING - PHASE ONE* To install fire sprinkler protection which includes the 6" underground supply, 6" riser, and extend protection piping and appurtenance into the 4,883 ft/2 area within the interior of the existing warehouse of cooled space per plans on file. Existing building area noted by architect (Charles Filanowicz) as 50,177 ft/2. This building did NOT have fire sprinkler protection to meet UBC, UFC requirements. OWNER HAS AGREED TO ADD FIRE SPRINKLERS TO THE BUILDING WITHIN A FIVE YEAR PLAN IN ORDER TO MEET FIRE DEPARTMENT REQUIREMENT FOR HIGH PILED STORAGE. THIS AGREEMENT IS ON FILE AND SIGNED BY THE OWNER AND DAVE MILLER. This permit is not attached to a building permit, but would be related to BLD00-03671. *JWA*
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  7/31/2001 PASS
DetailsJoe Tawney
Finaled for Joe Tawney per response (email) 07/31/01.
INSP-Final Inspection7/25/20017/26/20017/26/2001APASS
DetailsJoe Tawney
Final Pass OK for certificate of completion 7/26/2001 2:39:52 PM
INSP-Sprinkler Rough-in/Hydro7/25/20017/26/20017/26/2001APASS
DetailsJoe Tawney
OK on spklr rough in and OK on above ground hydro test 7/26/2001 2:40:30 PM
INSP-Supply line flush7/25/20017/26/20017/25/2001ACANC
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 07/25/2001 at 14:53:50. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 07/25/2001 at 14:54:43.
INSP-Final Inspection7/24/20017/25/20017/25/2001PNR
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 07/24/2001 at 13:59:18. Contact: ###-####.
INSP-Sprinkler Rough-in/Hydro7/24/20017/25/20017/25/2001APART
DetailsJoe Tawney
OK on spklr rough in add earthquake bracing and change two hangers 7/25/2001 2:17:08 PM
INSP-Supply line flush7/20/20017/23/20017/23/2001APASS
DetailsJoe Tawney
OK on supply line hydro test 7/23/2001 5:30:07 PM
INSP-Sprinkler Rough-in/Hydro7/20/20017/20/20017/20/2001PNR
DetailsRick Jackson
Scheduled by a contractor via Hello! on 07/20/2001 at 10:06:20. Contact: ###-####. will reschedule for 7/23 7/20/2001 3:57:42 PM
INSP-Sprinkler Rough-in/Hydro7/18/20017/19/20017/19/2001AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 07/18/2001 at 15:17:40. Contact: ###-####. underground hydro failed. leak at riser. 7/19/2001 11:11:28 AM
INSP-Supply line flush7/17/20017/17/20017/17/2001PPART
DetailsJoe Tawney
OK on supply line flush 7/17/2001 10:36:47 AM
INSP-Supply line flush7/16/20017/16/20017/16/2001PCANC
DetailsJoe Tawney
Cancel Water not turned on 7/16/2001 1:27:30 PM
INSP-Supply line flush7/10/20017/10/20017/10/2001PPART
DetailsJoe Tawney
OK to cover spklr supply line 7/10/2001 1:33:44 PM