Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR01-00364
StatusFinaled
Name COMMERCIAL FIRE PROTECTION
Site Address 1689 W SHORELINE Unit: DR
Project NameSPR RIVER WALK APTS O.H.
Customer Number 
ePlanReview 
Description
River Walk Apartments * To install fire sprinklers and standpipe system per NFPA 13-1999, 14-2000 & UFC-1997 Standards, in the parking garage (BLD00-03519), building section #1 per NFPA 13R-1999, 14-2000 & UFC-1997 Standards (BLD01-00531), building section #2 per NFPA 13R-1999, 14-2000 & UFC-1997 Standards (BLD01-000-1), building section #3 per NFPA 13R-1999, 14-2000 & UFC-1997 Standards (BLD01-0000). Two hour area separation are to be constructed to divide this apartment building into separate buildings (per UBC).
Section #1 is three stories, 33 units, above the three hour occupancy separation per UBC Section 311.2.2.1. The first floor is 9.837 ft/2, the second is 9,837 ft/2, the third floor is 9,837 ft/2. with 1,500 ft/2 for mezzanines.
Section #2 is three stories, 12 units, above the three hour occupancy separation per UBC Section 311.2.2.1. The first floor is 3,620 ft/2, the second is 3,620 ft/2, the third floor is 3,620 ft/2, and 500 ft/2. for mezzanines.
Section #3 is three stories, 30 units, above the three hour occupancy separation per UBC Section 311.2.2.1. The first floor is 9,230 ft/2, the second is 9,230 ft/2, the third floor is 9,230 ft/2 with 1,365 ft/2 for mezzanines.
NOTE: This building is fire sprinklered with a NFPA 13R system, with an approved alternate for installation of sprinkler heads at each side of area separation wall, to replace doors across exterior exit balconies. All work per the approved plans, attached comment list and the UFC. System installation shall be per related/correlated and adopted NFPA pamphlets, as regulated by the fire department. Underground fire line supply was installed under: FIR01-00159. Grading permit is: BLD00-03479. *JWA*
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Sprinkler Rough-in/Hydro3/26/20023/26/20023/26/2002APASS
DetailsRick Jackson
Added by Inspector: 409 On 3/26/2002 11:44:56 AM
INSP-Final Inspection1/16/20021/16/20021/16/2002PPART
DetailsRick Jackson
Added by Inspector: 409 On 1/16/2002 1:59:06 PM okay on this permit only
INSP-Final Inspection12/24/200112/26/200112/26/2001AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 12/24/2001 at 08:14:46. Contact: ###-####. need occupancy separation heads complete; esctcheons; need calc sticker; bell sticker and test alarms 12/26/2001 1:23:49 PM
INSP-Sprinkler Rough-in/Hydro12/26/200112/26/200112/26/2001PPART
DetailsRick Jackson
Added by Inspector: 409 On 12/26/2001 1:24:10 PM hydro okay on dry standpipe
INSP-Sprinkler Rough-in/Hydro10/2/200110/2/200110/2/2001PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/02/2001 at 10:18:17. Contact: ###-####. tenting not complete on east side; okay to cover other rooms 10/2/2001 2:43:07 PM
INSP-Sprinkler Rough-in/Hydro9/28/20019/28/20019/28/2001PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 09/28/2001 at 08:58:42. Contact: ###-####. batting for attic piping not complete; straps on west side 9/28/2001 2:49:38 PM
INSP-Sprinkler Rough-in/Hydro9/26/20019/27/20019/27/2001AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 09/26/2001 at 14:09:50. Contact: ###-####. straps throughout; tenting required 9/27/2001 11:13:35 AM
INSP-Sprinkler Rough-in/Hydro9/25/20019/26/20019/26/2001APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 09/25/2001 at 14:28:13. Contact: ###-####. hydro okay on aprtial part of system 9/26/2001 3:42:07 PM
INSP-Supply line flush9/12/20019/12/20019/12/2001PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 09/12/2001 at 10:59:09. Contact: ###-####.
INSP-Conference9/10/20019/10/20019/10/2001PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 09/10/2001 at 09:14:50. Contact: ###-####. discussed obstructions with Terry 9/10/2001 11:21:00 AM
INSP-Sprinkler Rough-in/Hydro8/31/20018/31/20018/31/2001PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 08/31/2001 at 07:40:18. Contact: ###-####. hydro for sidewall okay 8/31/2001 11:23:33 AM
INSP-Sprinkler Rough-in/Hydro8/23/20018/24/20018/24/2001PPART
DetailsJoe Tawney
OK on above ground hydro test for North half of bldg. Spklr rough in of North half. Address coverage along soffits installed for HVAC. Provide coverage info for side wall heads at separation walls. Do not cover lines requiring tenting. 8/24/2001 5:54:00 PM