Permit Information
Permit NumberFIR01-00427
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1472 S LOGGERS POND PL
Project NameSPR RIVER QUARRY APARTMENTS II
Customer Number 
ePlanReview 
Description
BUILDING # 22 TYPE II, 12 UNITS * (FP 3 of 5) TO INSTALL THE UNDERGROUND SUPPLY AND OVERHEAD FIRE SPRINKLERS IN A NEW THREE STORY, WOOD FRAMED, TYPE V ONE-HOUR, 12 UNIT APARTMENT BUILDING. THE FIRST FLOOR CONTAINS 4-ONE BEDROOM, ONE BATHROOM @ 790 FT/2 EACH WITHIN 2684 FT/2 GARAGE AREA. THE SECOND FLOOR CONTAINS 3-TWO BEDROOM TWO BATHROOM UNIT @ 1146 FT/2 EACH. 1- THREE BEDROOM TWO BATHROOM UNIT @ 1344 FT/2. THE THIRD FLOOR CONTAINS 3-TWO BEDROOM TWO BATHROOM UNIT @ 1146FT/2 EACH AND 1-THREE BEDROOM TWO BATHROOM UNIT AT 1344 FT/2. THE FIRST FLOOR IS APPROXIMATELY 3160 FT/2 FOR LIVING AREA. THE SECOND FLOOR IS APPROXIMATELY 4782 FT/2 OF LIVING AREA. THE THIRD FLOOR IS APPROXIMATELY 4782 FT/2. THE INSTALLATION OF A NFPA 13-R FIRE SPRINKLER SYSTEM IS REQUIRED AND CANNOT BE USED FOR ANY REDUCTION OF BUILDING CODE REQUIREMENTS. ALL CONSTRUCTION PER PLANS, ATTACHED COMMENT LIST AND THE 1997 EDITION OF THE UFC AS REGULATED BY THE FIRE DEPARTMENT. THIS PERMIT (WHICH INCLUDING THE UNDERGROUND SUPPLY), IS ATTACHED TO BUILDING PERMIT: BLD01-00646.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/12/20026/12/20026/12/2002PPASS
DetailsRick Jackson
Added by Inspector: 409 On 6/12/2002 1:16:28 PM
INSP-Sprinkler Rough-in/Hydro6/11/20026/12/20026/12/2002APASS
DetailsRick Jackson
TRENT ###-####
INSP-Supply line flush3/11/20023/12/20023/12/2002PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 03/11/2002 at 12:25:12. Contact: ###-####. flow still very low 3/12/2002 4:26:52 PM
INSP-Sprinkler Rough-in/Hydro1/29/20021/29/20021/29/2002PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 01/29/2002 at 09:28:00. Contact: ###-####. okay ro cover - r/i okay; still need hydro; underground will need flush and hydro 1/29/2002 3:01:56 PM
INSP-Supply line flush1/11/20021/14/20021/15/2002AFAIL
DetailsRick Jackson
Scheduled by Inspector: 409 On 1/11/2002 2:15:53 PM received a call from Dan with Shilo. He said the other underground supplies were flushed and they produced a lot more water than this one and they will proceed with other trouble shooting to determine why this flush is so low on flow 1/15/2002 11:50:37 AM
INSP-Supply line flush1/10/20021/11/20021/11/2002PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 01/10/2002 at 14:02:42. Contact: ###-####. very limited flow on underground flush. shilo to retest other buildings up stream from this building on monday 1/14 1/11/2002 2:15:30 PM
INSP-Sprinkler Rough-in10/10/200110/10/200110/10/2001PPART
DetailsRick Jackson
###-#### underground flush only - pass 10/10/2001 3:15:35 PM
INSP-Sprinkler Rough-in10/8/200110/8/200110/8/2001PNR
DetailsRick Jackson
mike ###-#### underground
INSP-Sprinkler Rough-in/Hydro8/17/20018/17/20018/17/2001PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 08/17/2001 at 08:16:36. Contact: ###-####. underground okay to cover 8/17/2001 1:10:23 PM