INSP-Final Inspection | 12/17/2001 | 12/17/2001 | 12/17/2001 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 12/17/2001 10:51:54 AM
|
INSP-Sprinkler Rough-in/Hydro | 12/17/2001 | 12/17/2001 | 12/17/2001 | A | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 12/17/2001 10:51:34 AM hydro okay
|
INSP-Supply line flush | 12/12/2001 | 12/13/2001 | 12/13/2001 | A | PASS |
Rick Jackson
|
|
|
###-#### MIKE
|
INSP-Sprinkler Rough-in | 10/17/2001 | 10/17/2001 | 10/17/2001 | P | PART |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 10/17/2001 3:06:14 PM resubmittal required due to change of fire service main; okay to cover 10/17/2001 3:19:49 PM
|
INSP-Sprinkler Rough-in | 8/13/2001 | 8/13/2001 | 8/13/2001 | A | PART |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 8/13/2001 9:25:52 AM okay to cover 6 inch supply line only; thrust blocks installed and clearance at floor provided by insulation 8/13/2001 10:08:56 AM
|