Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR01-00504
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 190 E FRONT ST
Project NameSPR CIVIC PLAZA PARKING GARAGE
Customer Number 
ePlanReview 
Description
CIVIC PLAZA PUBLIC PARKING GARAGE - TO FIRE SPRINKLER PER NFPA 13, 14, 24, 72, A NEW 109,660 ft/2, THREE TIER PARKING GARAGE WITH A 41,600 ft/2, BASEMENT. THIS PARKING GARAGE WILL HAVE 432 TOTAL PARKING SPACES. THIS BUILDING INCLUDES A 20,225 ft/2 AREA AT THE SOUTH SIDE OF THE GROUND LEVEL, THAT IS BEING CONSTRUCTED AS A SHELL AREA FOR FUTURE FINISH AS RETAIL TENANT SPACE. THIS BUILDING IS FULLY FIRE SPRINKLERED. SEPARATE TENANT IMPROVEMENT FIRE PERMITS MAY BE REQUIRED TO FINISH THE RETAIL SPACES FOR OCCUPANCY. ALL CONSTRUCTION PER PLANS AND ATTACHED REVIEW NOTES, RELATED AND ADOPTED NFPA PAMPHLETS AS DIRECTED BY THE UFC AND REGULATED BY THE FIRE DEPARTMENT. THIS BUILDING IS BEING CONSTRUCTED WITH A STRUCTURAL SUPPORT DECK FOR A POSSIBLE FUTURE EXPANSION. UNDERGROUND FIRE PERMIT IS: FIR01-00264. THIS FIRE PERMIT IS ATTACHED TO BLD01-03538. (JWA)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/26/200211/27/200211/27/2002APASS
DetailsRick Jackson
forest says its not finaled yet ###-#### trip test of all dry systems completed; all under a minute 11/27/2002 2:09:42 PM
INSP-Alarm Testing9/26/20029/27/20029/27/2002ANR
DetailsRick Jackson
###-#### willreschedule for next week; need additional personnel to test 9/27/2002 10:11:34 AM
INSP-Sprinkler Rough-in/Hydro9/20/20029/23/20029/23/2002PPART
DetailsRick Jackson
###-#### hydro okay on the five systems; still need to trip test 9/23/2002 3:40:02 PM
INSP-Final Inspection9/11/20029/13/20029/13/2002PFAIL
DetailsRick Jackson
###-#### attempted hydro on all systems; numerous leaks; will try again next week 9/16/2002 8:34:35 AM
INSP-Final Inspection1/9/20021/10/20021/10/2002AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 01/09/2002 at 15:05:57. Contact: ###-####. all tampers/flows, etc tested okay. need to add head in small room in basement and additional drain 1/10/2002 12:06:58 PM
INSP-Sprinkler Rough-in/Hydro1/3/20021/4/20021/4/2002PPART
DetailsRick Jackson
Scheduled by Inspector: 409 On 1/3/2002 2:41:40 PM last riser passed 24 hour air test 1/4/2002 3:02:34 PM
INSP-Sprinkler Rough-in/Hydro1/3/20021/3/20021/3/2002PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 01/03/2002 at 10:48:01. Contact: ###-####. start of 24 hr test of last system on riser 4 1/3/2002 2:46:35 PM
INSP-Sprinkler Rough-in/Hydro12/27/200112/28/200112/28/2001APART
DetailsRick Jackson
Scheduled by Inspector: 409 On 12/27/2001 1:06:04 PM all air test complete except the system for floor two 12/28/2001 9:02:39 AM
INSP-Sprinkler Rough-in/Hydro12/26/200112/26/200112/27/2001PFAIL
DetailsRick Jackson
###-#### slope of mains on south side on all floors not sloped back to east sides; air test started at 8:00 am for three risers on west wall of riser room - will return on 11/28 at 8 am 12/27/2001 1:08:29 PM
INSP-Sprinkler Rough-in12/11/200112/11/200112/11/2001PFAIL
DetailsRick Jackson
###-#### need comments for approved plans; plans on site but no comments - couldn't locate comments 12/12/2001 4:59:05 AM