INSP-Final Inspection | 9/26/2002 | 9/26/2002 | 9/26/2002 | P | PASS |
Troy Cobbley
|
|
|
fire sprinkler system finaled
|
INSP-Final Inspection | 9/24/2002 | 9/24/2002 | 9/24/2002 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 09/24/2002 at 10:45:28. Contact: ###-####. tested tampers/flows okay; need chain/lock on PIV; splash gaurd at inspectors test as shown on plans 9/24/2002 3:13:11 PM
|
INSP-Sprinkler Rough-in | 7/10/2002 | 7/10/2002 | 7/10/2002 | A | FAIL |
Troy Cobbley
|
|
|
All items on the correction notice for the dry system rough-in have been corrected except for protection that needs to be provided in the overbuild areas above the riser room
|
INSP-Sprinkler Rough-in | 6/7/2002 | 6/7/2002 | 6/7/2002 | A | PART |
Troy Cobbley
|
|
|
wet system rough-in ok. Only a small section of the attic dry system was inspected. It had multiple problems so no other areas were looked at. Problems included sprinkler heads spaced too close, heads too far from deck, missing earth quake bracing and head overspaced off of a draft stop and installation of sprinklers in the hydraulic calc area not per plan. I left comment for that area to be resubmitted for Bill Alexanders approval
|
INSP-Sprinkler Rough-in | 6/4/2002 | 6/4/2002 | 6/4/2002 | A | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 6/4/2002 10:27:15 AM okay to cover sanctuary only; fire treated plywood used
|
INSP-Sprinkler Rough-in | 5/8/2002 | 5/8/2002 | 5/8/2002 | A | PART |
Troy Cobbley
|
|
|
Restrooms located in northwest corner of buildings ok to cover
|