INSP-Sprinkler Rough-in/Hydro | 8/9/2002 | 8/12/2002 | 8/12/2002 | A | PASS |
Troy Cobbley
|
|
|
hydro test for the overhead system is OK. Permit also finaled 8/12/2002 4:42:47 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/8/2002 | 8/9/2002 | 8/9/2002 | A | FAIL |
Troy Cobbley
|
|
|
above ground hydro test failed 8/9/2002 2:11:09 PM
|
INSP-Supply line flush | 8/8/2002 | 8/8/2002 | 8/8/2002 | P | PASS |
Troy Cobbley
|
|
|
flush OK
|
INSP-Sprinkler Rough-in | 7/17/2002 | 7/17/2002 | 7/17/2002 | A | PASS |
Troy Cobbley
|
|
|
Underground thrust block ok for cover
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2002 | 7/11/2002 | 7/11/2002 | A | PASS |
Troy Cobbley
|
|
|
Underground supply OK to cover
|
INSP-Supply line flush | 7/11/2002 | 7/11/2002 | 7/11/2002 | P | CANC |
Troy Cobbley
|
|
|
duplicate inspection 7/11/2002 3:24:25 PM
|
INSP-Supply line flush | 6/27/2002 | 6/28/2002 | 6/28/2002 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for the stub out only. The thrust blocking and beding is OK but the nuts and bolts need the non corrosive covering. Contractor said it would be taken care of monday 6/28/2002 2:56:37 PM
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2002 | 6/28/2002 | 6/27/2002 | A | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 06/27/2002 at 13:26:24. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 06/27/2002 at 13:27:22.
|
INSP-Sprinkler Rough-in | 5/13/2002 | 5/14/2002 | 5/14/2002 | P | PART |
Rick Jackson
|
|
|
r/i- ###-####- bruce Modules A-B-C okay; plans kept in Tom's office; all areas above finsihed ceiling are sheetrocked 5/14/2002 4:03:04 PM
|