Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR02-00130
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 8000 S FEDERAL WAY
Project NameSPR MICRON MASK SHOP
Customer Number 
ePlanReview 
Description
MICRON MASK SHOP TENANT IMPROVEMENT (PCS #80-20003278) * TO INSTALL 5 COMPLETE WET FIRE SPRINKLER SYSTEMS IN AN 80,350 FT/2, TWO STORY STRUCTURE WITH 26,870 FT/2 BASEMENT, MICRON MASK SHOP, FOR FABRICATION AND OFFICE OCCUPANCY. THIS BUILDING WILL CONTAIN A 13,725 FT/2 OFFICE AREA AND THE REMAINDER OF TWO STORIES AND BASEMENT WILL BE FABRICATION AND STORAGE AREAS. THE BASEMENT AREAS ARE PRIMARILY NORMALLY UNOCCUPIED CHEMICAL STORAGE, SUPPLY AND RECOVERY AREAS. THE SECOND FLOOR IS PRIMARILY NORMALLY UNOCCUPIED MECHANICAL AND FAN DECK AREAS. THIS FACILITY IS FULLY SPRINKLERED. THE FIRE SPRINKLER SYSTEM SHALL COMPLY WITH THE UFC-1997, NFPA 13-1999, 318-2000, RED-LINED PLANS, ATTACHED REVIEW COMMENT AND CONDITIONS LIST; AS REGULATED BY THE FIRE CHIEF. AN APPROVED AND STAMPED PLAN, PERMIT AND FIRE "INSPECTION CARD" IS REQUIRED ON SITE AS A CONDITION OF THIS PERMIT; TO PROVIDE WITNESS OF COMPLIANCE TO THIS WORK. UNDERGROUND FIRE SERVICE SUPPLY WAS PERMITTED UNDER: FIR02-00098. THE SHELL BUILDING WAS CONSTRUCTED UNDER PERMIT BLD01-02222. THIS FIRE SPRINKLER PERMIT IS ATTACHED TO TENANT IMPROVEMENT BUILDING PERMIT: BLD01-02848.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/14/200210/14/200210/14/2002PPASS
DetailsRick Jackson
INSP-Final Inspection10/4/200210/7/200210/7/2002APART
DetailsRick Jackson
to mainly review cleanroom walls and protection under ducts. Jonathon Lee foreman on site; Phone #: ###-#### Internet Inspection Request from: Trent Bice okay per plans; need info on work in corridor used for tool wipe down area; EQ on main riser to wall 10/7/2002 3:04:05 PM
INSP-Final Inspection10/4/200210/4/200210/4/2002ACANC
DetailsRick Jackson
Jonathon lee foreman on site. Clean room and fan attic.; Phone #: ###-#### Internet Inspection Request from: Trent Bice Inspection cancelled from web by: Trent Bice
INSP-Sprinkler Rough-in/Hydro7/3/20027/8/20027/8/2002PCANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 07/03/2002 at 14:10:20. Contact: ###-####.cancel per chris
INSP-Sprinkler Rough-in/Hydro7/8/20027/8/20027/8/2002PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 07/08/2002 at 10:04:03. Contact: ###-####. all systems hydro okay 7/8/2002 4:51:04 PM
INSP-Sprinkler Rough-in/Hydro6/26/20026/27/20026/27/2002PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 06/26/2002 at 15:38:54. Contact: ###-####. all deficiencies corrected; awaiting heads for drops to hydro all systems and test alarms 6/27/2002 5:00:18 PM
INSP-Sprinkler Rough-in/Hydro6/26/20026/26/20026/26/2002PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 06/26/2002 at 10:04:09. Contact: ###-####. all items corrected from previous inspections; need to sprinkler above corridor in sub fab area 6/27/2002 7:00:48 AM
INSP-Sprinkler Rough-in/Hydro6/24/20026/25/20026/25/2002PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 06/24/2002 at 14:54:55. Contact: ###-####. eq on main feed and FDC; need walls at AHU in basement 6/25/2002 4:33:54 PM
INSP-Sprinkler Rough-in/Hydro6/24/20026/24/20026/24/2002PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 06/24/2002 at 08:09:43. Contact: ###-####. straps; hangers and several obstructions 6/25/2002 7:06:36 AM
INSP-Sprinkler Rough-in/Hydro6/19/20026/21/20026/21/2002ACANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 06/19/2002 at 16:33:59. Contact: ###-####. I ran out of time today; will reschedule for 6/24 6/21/2002 4:02:38 PM
INSP-Sprinkler Rough-in/Hydro6/18/20026/19/20026/19/2002PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 06/18/2002 at 16:33:28. Contact: ###-####. hangers in office area; clean has modifications to plans - need to resubmit with clacs for review and approval; will continue inspection on 6/20 6/19/2002 4:02:29 PM
INSP-Sprinkler Rough-in/Hydro6/17/20026/18/20026/18/2002PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 06/17/2002 at 16:56:27. Contact: ###-####. met with Mike; will need resubmittals for clean room 6/18/2002 4:52:27 PM
INSP-Sprinkler Rough-in/Hydro6/13/20026/14/20026/14/2002PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 06/13/2002 at 08:18:42. Contact: ###-####. received call from Mike of Shilo and he said he wouldn't be there and he would reschedule for next week; went to job trailer and reviewed plans; left c/n with Les about having provisions to test flow switches in gas rooms 6/14/2002 3:49:18 PM