INSP-Final Inspection | 5/9/2003 | 5/9/2003 | 5/9/2003 | A | PASS |
Troy Cobbley
|
|
|
|
INSP-Sprinkler Rough-in | 7/2/2002 | 7/3/2002 | 7/3/2002 | P | PASS |
Troy Cobbley
|
|
|
rough-in for canopy is OK. Ok for cover 7/3/2002 3:19:06 PM
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2002 | 7/2/2002 | 7/2/2002 | A | FAIL |
Troy Cobbley
|
|
|
hangers over the tax office still need to be relocated. Hydro test for the dry system is OK 7/2/2002 2:20:43 PM 7/2/2002 2:21:02 PM
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2002 | 6/28/2002 | 6/28/2002 | A | FAIL |
Troy Cobbley
|
|
|
hydro test failed. Repair leaks, remove wire from the pipe, alin upright head in attic space with the deck slope, attach hangers and longitudinal EQ braces to the top chord of trusses instead of the bottom chord, retest system and reinspect 6/28/2002 11:22:05 AM
|