INSP-Final Inspection | 8/22/2002 | 8/22/2002 | 8/22/2002 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinklers finaled 8/23/2002 11:17:14 AM
|
INSP-Sprinkler Rough-in/Hydro | 8/19/2002 | 8/20/2002 | 8/20/2002 | A | PASS |
Troy Cobbley
|
|
|
System #3 aboveground hydro test OK but was witnessed by the general contractor. Roughin in gym and auditorium ok except for thru bolts are required for the EQ attachments to the brick walls 8/20/2002 4:06:20 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/2/2002 | 8/2/2002 | 8/2/2002 | P | PASS |
Troy Cobbley
|
|
|
areas 3d and 3f OK to cover. System #2 hydro test OK 8/2/2002 2:37:38 PM
|
INSP-Sprinkler Rough-in/Hydro | 7/24/2002 | 7/25/2002 | 7/25/2002 | A | PASS |
Troy Cobbley
|
|
|
hydro test for the underground, fdc, riser header and the overhead system east area OK 7/25/2002 1:18:48 PM
|
INSP-Supply line flush | 7/24/2002 | 7/25/2002 | 7/25/2002 | A | PASS |
Troy Cobbley
|
|
|
flush of underground OK 7/25/2002 9:08:41 AM
|
INSP-Sprinkler Rough-in | 7/22/2002 | 7/23/2002 | 7/23/2002 | A | PART |
Troy Cobbley
|
|
|
Multiple areas OK for cover. See on site approved plans for specific areas approved for cover 7/23/2002 2:26:47 PM
|
INSP-Supply line flush | 7/2/2002 | 7/3/2002 | 7/3/2002 | P | PART |
Troy Cobbley
|
|
|
supply line and FDC are ok for cover. They both still need to be hydro tested and flushed 7/3/2002 1:50:15 PM
|
INSP-Supply line flush | 6/27/2002 | 6/28/2002 | 6/28/2002 | A | PASS |
Troy Cobbley
|
|
|
Underground OK to cover. Hydro or flush not done 6/28/2002 11:42:35 AM
|