Permit Information
Permit NumberFIR02-00217
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 13600 W MCMILLAN RD
Project NameSPR LOWELL SCOTT
Customer Number 
ePlanReview 
Description
(Lowell Scott Middle School Remodel) - To install 3 complete wet pipe fire sprinkler protection systems throughout this facility, which includes approximately 300'-0" of 6" C-900 and D.I. underground and remote (accessible) FDC; to comply with Life Safety upgrade requirements. Other building upgrades includes classroom remodels, area separations, new mechanical systems, new fire alarm, new handicapped restrooms and misc. other improvements addressed in the building permit BLD02-00937 (which this fire permit is attached). Fire sprinklers are being used for special approval as an alternate to comply with the 2000 IBC for Area and Exit provisions, per T. Hogland, (letter attached to building permit plans). All fire sprinkler installation and work must comply with NFPA 13-1999, the UFC-1997, attached review comment and conditions list, as regulated by the Fire Chief. These review comments, approved/stamped plans, permit and fire inspection signoff card are required to be on site at all times, as a condition of this work scope, to provide witness of compliance verification of minimum code.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/22/20028/22/20028/22/2002PPASS
DetailsTroy Cobbley
Fire sprinklers finaled 8/23/2002 11:17:14 AM
INSP-Sprinkler Rough-in/Hydro8/19/20028/20/20028/20/2002APASS
DetailsTroy Cobbley
System #3 aboveground hydro test OK but was witnessed by the general contractor. Roughin in gym and auditorium ok except for thru bolts are required for the EQ attachments to the brick walls 8/20/2002 4:06:20 PM
INSP-Sprinkler Rough-in/Hydro8/2/20028/2/20028/2/2002PPASS
DetailsTroy Cobbley
areas 3d and 3f OK to cover. System #2 hydro test OK 8/2/2002 2:37:38 PM
INSP-Sprinkler Rough-in/Hydro7/24/20027/25/20027/25/2002APASS
DetailsTroy Cobbley
hydro test for the underground, fdc, riser header and the overhead system east area OK 7/25/2002 1:18:48 PM
INSP-Supply line flush7/24/20027/25/20027/25/2002APASS
DetailsTroy Cobbley
flush of underground OK 7/25/2002 9:08:41 AM
INSP-Sprinkler Rough-in7/22/20027/23/20027/23/2002APART
DetailsTroy Cobbley
Multiple areas OK for cover. See on site approved plans for specific areas approved for cover 7/23/2002 2:26:47 PM
INSP-Supply line flush7/2/20027/3/20027/3/2002PPART
DetailsTroy Cobbley
supply line and FDC are ok for cover. They both still need to be hydro tested and flushed 7/3/2002 1:50:15 PM
INSP-Supply line flush6/27/20026/28/20026/28/2002APASS
DetailsTroy Cobbley
Underground OK to cover. Hydro or flush not done 6/28/2002 11:42:35 AM