Permit NumberFIR02-00304
StatusFinaled
Name DE BEST FIRE PROTECTION
Site Address 12639 W EXPLORER ST
Project NameSPR Morton Dev. Office (She
Customer Number 
ePlanReview 
Description
Boise Research Center * Morton Development Office (Shell & Core) - To install a complete, fully protected, Light Hazard Occupancy fire sprinkler system a new 23,125 square foot, two story office Shell & Core building, (less underground supply-FIR02-00178). This building is constructed of concrete tilt-up exterior walls with interior steel structural columns and steel roof joist with metal roof deck. This building is fully fire sprinklered. The sprinklers are used for area increase. This is a shell and core permit only. Tenant Improvements shall require separate fire permitting. No occupancy is allowed under the building permit, this fire permit is attached. First floor: 11,760 ft/2, Second floor: 11,365 ft/2. All fire sprinkler system work shall comply with NFPA 13?1999, attached review comment and conditions list; as regulated by the fire chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD01-02513.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/24/200210/24/200210/24/2002PPASS
DetailsTroy Cobbley
fire finaled
INSP-Sprinkler Rough-in/Hydro10/17/200210/17/200210/17/2002APASS
DetailsTroy Cobbley
above ground hydro test is OK
INSP-Final Inspection10/16/200210/16/200210/16/2002PFAIL
DetailsTroy Cobbley
all items on the correction notice have been taken care of except for the addition of heads over the egress corridor and the lobbies
INSP-Sprinkler Rough-in10/14/200210/14/200210/14/2002PFAIL
DetailsTroy Cobbley
provide additional hangers in 1st floor corridor, provide 4 way eq bracing in the northwest corner of the 2nd floor, provide upright instead of a pendant head in the 1st floor electrical room, provide adequate sprinkler coverage over lobby/egress corridor on the 1st floor.