INSP-Final Inspection | 9/4/2002 | 9/4/2002 | 9/4/2002 | A | PASS |
Rick Jackson
|
|
|
tested dry system trip test and alarms/tampers - okay
|
INSP-Sprinkler Rough-in/Hydro | 8/28/2002 | 8/29/2002 | 8/29/2002 | A | PART |
Rick Jackson
|
|
|
overhead hydro okay on system in gym under bleachers in shower/locker room only 8/29/2002 10:59:04 AM
|
INSP-Sprinkler Rough-in/Hydro | 8/28/2002 | 8/28/2002 | 8/28/2002 | P | FAIL |
Rick Jackson
|
|
|
hydro on area in gym and under seats wouldn't hold pressure
|
INSP-Sprinkler Rough-in/Hydro | 8/22/2002 | 8/23/2002 | 8/23/2002 | P | PART |
Rick Jackson
|
|
|
air test 24 hour air test okay on dry system 8/23/2002 1:28:18 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/22/2002 | 8/23/2002 | 8/23/2002 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/22/2002 at 16:07:34. Contact: ###-####. hydro on all overhead okay; tested wet system alarms okay; need to test dry system alarms/tampers; dry uprights not installed 8/26/2002 8:37:42 AM
|
INSP-Sprinkler Rough-in/Hydro | 8/21/2002 | 8/22/2002 | 8/22/2002 | A | PART |
Rick Jackson
|
|
|
###-#### LONNY started 24 hr air test 8/22/2002 3:47:55 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/16/2002 | 8/19/2002 | 8/19/2002 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/16/2002 at 14:06:03. Contact: ###-####. okay to cover west existing areas; dry valve not complete; will need to reverify combustibles sheet rocked in corridors on both floors 8/19/2002 3:52:14 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/14/2002 | 8/15/2002 | 8/15/2002 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/14/2002 at 11:34:00. Contact: ###-####. 4 inch main requires hangers per TJI instrcutions; need proper temp heads in west stair; complete EQ'ing; storage under heads in classrooms within 18 inches of head due to shelf; this covers only the west existing portion, new addition and gym not ready 8/15/2002 12:01:05 PM
|