Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR02-00309
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 825 W FORT ST
Project NameSPR ST JOSEPH'S SCHOOL
Customer Number 
ePlanReview 
Description
St. Joseph's School * To install a new fire sprinkler system in a 22,077 ft/2 school which includes a 6,859 ft/2 (3,430 ft/2 1st floor, 3,429 2nd floor) two story, Type V 1hr classroom addition, between the existing classrooms and gymnasium. The new addition work includes five classroom, a media center expansion, a storeroom, new ramp, and a new elevator. Fire sprinklers system will be used for substitution of one-hour construction. The fire sprinkler system work shall comply with NFPA 13-1999, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. Underground fire service supply was permitted under FIR02-00265. This permit is attached to building permit: BLD02-00505.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/4/20029/4/20029/4/2002APASS
DetailsRick Jackson
tested dry system trip test and alarms/tampers - okay
INSP-Sprinkler Rough-in/Hydro8/28/20028/29/20028/29/2002APART
DetailsRick Jackson
overhead hydro okay on system in gym under bleachers in shower/locker room only 8/29/2002 10:59:04 AM
INSP-Sprinkler Rough-in/Hydro8/28/20028/28/20028/28/2002PFAIL
DetailsRick Jackson
hydro on area in gym and under seats wouldn't hold pressure
INSP-Sprinkler Rough-in/Hydro8/22/20028/23/20028/23/2002PPART
DetailsRick Jackson
air test 24 hour air test okay on dry system 8/23/2002 1:28:18 PM
INSP-Sprinkler Rough-in/Hydro8/22/20028/23/20028/23/2002APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 08/22/2002 at 16:07:34. Contact: ###-####. hydro on all overhead okay; tested wet system alarms okay; need to test dry system alarms/tampers; dry uprights not installed 8/26/2002 8:37:42 AM
INSP-Sprinkler Rough-in/Hydro8/21/20028/22/20028/22/2002APART
DetailsRick Jackson
###-#### LONNY started 24 hr air test 8/22/2002 3:47:55 PM
INSP-Sprinkler Rough-in/Hydro8/16/20028/19/20028/19/2002APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 08/16/2002 at 14:06:03. Contact: ###-####. okay to cover west existing areas; dry valve not complete; will need to reverify combustibles sheet rocked in corridors on both floors 8/19/2002 3:52:14 PM
INSP-Sprinkler Rough-in/Hydro8/14/20028/15/20028/15/2002AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 08/14/2002 at 11:34:00. Contact: ###-####. 4 inch main requires hangers per TJI instrcutions; need proper temp heads in west stair; complete EQ'ing; storage under heads in classrooms within 18 inches of head due to shelf; this covers only the west existing portion, new addition and gym not ready 8/15/2002 12:01:05 PM