INSP-Final Inspection | 5/14/2003 | 5/14/2003 | 5/14/2003 | P | PASS |
Troy Cobbley
|
|
|
fire alarms finaled 5/14/2003 10:50:46 AM
|
INSP-Final Inspection | 5/12/2003 | 5/13/2003 | 5/13/2003 | A | PART |
Troy Cobbley
|
|
|
The audio in the santuary does not meet the 75 db requirement. A temporary occupancy was given until the problem can be remedied. The temporary occupancy was given with Dave Millers permission 5/13/2003 10:27:45 AM
|
INSP-Final Inspection | 5/12/2003 | 5/12/2003 | 5/12/2003 | P | PASS |
Troy Cobbley
|
|
|
Retest the hood for light and recepticle shutdown. Provide panel keys for knox box. Provide map for facp. Provide room numbers on map. Lounge 130 pull station is mis labeled. Verify signals with fax 5/12/2003 3:23:41 PM
|
INSP-Final Inspection | 5/8/2003 | 5/9/2003 | 5/9/2003 | A | FAIL |
Troy Cobbley
|
|
|
Strobes exceed 15' from the ends of corridors and manual pull stations exceed 5' from door in several locations. Fire alarm system had a trouble generated from somewhere on the sprinkler system. No inspection done. See approved job site plans for specific locations. All fire sprinkler monitoring devices and alarm devices need tested 5/9/2003 11:42:22 AM
|
INSP-Conference | 2/12/2003 | 2/12/2003 | 2/12/2003 | A | DONE |
Troy Cobbley
|
|
|
I called Alarmco and spoke to Teresa about getting the alarm resubmittals in for review since it had been six months since their last submittals. Alarmco was on the job today.
|