Permit Information
Permit NumberFIR02-00347
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 391 N ANCESTOR PL
Project NameSPR EMERALD CENTER BLD #F
Customer Number 
ePlanReview 
Description
EMERALD TECH CENTER - BUILDING #F (SHELL) - To install underground and an OH-2 overhead fire sprinkler system, incorproating ECOH upright roof sprinklers, in a new new 25, 075 ft/2 one story, type VN, concrete tilt-up building with steel roof joist and metal roof deck. Underground includes approximately 135 feet of 6" C-900 PVC connected at the property line off Ancester Place, running west and entering the structure approximately 4'-0" west of column line "D". Also this permit includes a new fire hydrant tapped off the same street, running approximately 35 feet of C-900 PVC west and 25 feet north to an area off the north curb entry for fire apperatus access/use. This building is required to be fully fire sprinklered for area increase (per requirements of the UBC). Separate permits will be required to finish this building for occupancy. All fire sprinkler system installation work and equipment, materials and appurtenance shall comply with NFPA 13?1999, 24-1995, 72-1999 and related, the attached review comment and conditions list; as regulated by the Fire Chief. These notes, permit and fire Inspection Card are required to be on site as a condition of this work, to provide witness of compliance verification meeting minimum code. This permit is attached to building permit BLD02-00699.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/19/20043/19/20043/19/2004PPASS
DetailsTroy Cobbley
fire sprinklers finaled
INSP-Final Inspection3/18/20043/18/20043/18/2004PCANC
DetailsTroy Cobbley
forward flush
INSP-Sprinkler Rough-in/Hydro9/24/20029/25/20029/25/2002PPASS
DetailsTroy Cobbley
Above ground and underground hydro test OK. Above ground piping rough-in is OK. Drains, FDC and alarm still needs to be completed 9/26/2002 12:52:44 PM
INSP-Sprinkler Rough-in/Hydro9/25/20029/25/20029/25/2002PFAIL
DetailsTroy Cobbley
some of the retaining straps are not wraped around the trusses, the sprinkler pipe in the riser room can not be hung from the angle iron supports on the bottom of the trusses, move the hanger to the top of the truss, in the southeast corner of the building the 1 1/4" til back piece of pipe exceeds the 48" allowed for a unsupported arm over.
INSP-Sprinkler Rough-in/Hydro9/11/20029/12/20029/12/2002APART
DetailsTroy Cobbley
sprinkler rough in is not ready yet but the underground flush passed 9/12/2002 9:07:04 AM