INSP-Final Inspection | 5/6/2003 | 5/7/2003 | 5/7/2003 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinklers finaled 5/7/2003 2:21:34 PM
|
INSP-Final Inspection | 4/22/2003 | 4/23/2003 | 4/23/2003 | P | FAIL |
Troy Cobbley
|
|
|
TODD; Phone #: ###-#### Sprinkler heads are overspaced in the existing lobby, hangers to be attached to the top of the structure (see the detail on the approved drawings), provide eq straps on all piping in th escope of work, installation does not match approved plans. Review notes appear to state the max. head spacing to be 149 sq. ft. Pendants in the lobby exceed this. Provide approved drawings with the 1/6/03 date on them. These drawings are showing the work in the lobby area. The previous resubmittal drawings show existing heads only. The pendants installed now don't even match those locations 4/23/2003 10:13:52 AM
|
INSP-Final Inspection | 4/7/2003 | 4/7/2003 | 4/7/2003 | P | PART |
Troy Cobbley
|
|
|
Fire sprinklers given temp with dave millers permission. There is still some work in the lobby and a restroom that needs to be added near the lobby
|
INSP-Sprinkler Rough-in/Hydro | 3/20/2003 | 3/20/2003 | 3/20/2003 | P | PART |
Rick Jackson
|
|
|
TERRY; Phone #: ###-#### Internet Inspection Request from: Darla Downs hydro on overhead okay 3/20/2003 4:13:14 PM
|
INSP-Sprinkler Rough-in/Hydro | 3/18/2003 | 3/18/2003 | 3/18/2003 | P | PASS |
Troy Cobbley
|
|
|
Sprinklers are OK to cover. Provide one additional sprinkler pendant over the security desk 3/18/2003 2:00:35 PM
|