Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR02-00477
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 601 W GOWEN RD
Project NameSPR WPS Racking & Changes
Customer Number 
ePlanReview 
Description
* WESTERN POWER SPORTS * To modify and add fire sprinkler protection for added racking in a 106,964 ft/2 type II-N building permitted for B, S1, A3 occupancies. S1 includes High Piled Combustible Storage of Group "A" Plastics and Tire storage. This work entails modification to the existing fire sprinkler risers with the installation of a 100 gpm fire booster pump, jockey pump, controllers, modified roof protection for Tire Storage (for increase storage elevation), a 4th level of mezzanine racking, added racking over and existing concrete mezzanine and added face fire sprinkler protection. The fire sprinkler system installation and related work shall comply (but may not be limited) to: NFPA 13-1999, 20-1999, 72-1999, attached review comment and conditions list, as regulated by the Boise City Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is not attached to a building permit at this date. NOTE: The approval of this fire protection permit does not allow the actual installation of any added or modified and use of racking without the required building permit approval. Fire sprinkler shell (BLD01-00197) and original T.I. (BLD01-01238) was permitted under: FIR01-00031, which was connected to building shell permit: BLD01-00197. Underground fire line is existing and previously permitted under: FIR01-00096, connected to grading permit: BLD01-00094. Original racking permit done under BLD01-01592.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/8/200312/8/200312/8/2003PPASS
DetailsRick Jackson
INSP-Sprinkler Rough-in/Hydro11/17/200311/17/200311/17/2003PFAIL
DetailsRick Jackson
Would like to do final walk through on fire sprinklers and do flow test for fire pump. We would like to schedule the inspection at about 1:00 pm; Phone #: ###-#### Internet Inspection Request from: Trent Bice tested pump for flow at 150% and there is 25 psi on supply; will need pump certification papers; spare heads; sign on pump room door; no floor drain; 11/17/2003 4:59:26 PM
INSP-Sprinkler Rough-in/Hydro11/5/200311/6/200311/5/2003PCANC
DetailsRick Jackson
Please call 1 hour prior to arrival; Phone #: ###-#### Internet Inspection Request from: Trent Bice Inspection cancelled from web by: Trent Bice
INSP-Sprinkler Rough-in/Hydro8/14/20038/15/20038/15/2003PPART
DetailsRick Jackson
Call prior to arrival so that we can have system charged. Foremans name is Rudi.; Phone #: ###-#### Internet Inspection Request from: Trent Bice hydro on perimeter racking okay 8/15/2003 3:41:20 PM
INSP-Sprinkler Rough-in/Hydro7/28/20037/29/20037/29/2003APART
DetailsRick Jackson
third floor mezz okay; hose valves not completed for this level 7/29/2003 9:33:35 AM
INSP-Sprinkler Rough-in/Hydro7/28/20037/28/20037/28/2003PPART
DetailsRick Jackson
Please call 1 hour before inspection so we can set at 200lbs. Thank you ; Phone #: ###-#### Internet Inspection Request from: Trent Bice hydro on 3rd floor mezz okay; will continue rough in tomorrow 7/28/2003 3:32:26 PM
FIR-Aging Inspection7/9/20037/9/20037/9/2003 PASS
DetailsRick Jackson
talked to Trent and he said the work is in progress and they are 3 weeks out 7/10/2003 9:56:53 AM