INSP-Final Inspection | 7/1/2003 | 7/2/2003 | 7/2/2003 | P | PASS |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 7/1/2003 at 2:15:49 PM. Contact: ###-####.
|
INSP-Final Inspection | 7/1/2003 | 7/1/2003 | 7/1/2003 | P | FAIL |
Troy Cobbley
|
|
|
provide locks on the valves per the plan review notes and test flow switches 7/1/2003 3:34:41 PM
|
INSP-Final Inspection | 6/26/2003 | 6/27/2003 | 6/27/2003 | P | FAIL |
Troy Cobbley
|
|
|
Provide additional 175 pendants for the head box, provide the correct orfice in the inspectors test, provide steel pipe and standard pendant in the furnace room, flush underground, lock valves, replace painted pendants, pendant in the kitchen is blocked by a surface mounted light 6/27/2003 1:39:35 PM
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2003 | 6/20/2003 | 6/20/2003 | A | CANC |
Troy Cobbley
|
|
|
wrong inspection called in per Mike with Debest. This job is not ready yet 6/20/2003 8:50:03 AM
|
INSP-Sprinkler Rough-in | 5/12/2003 | 5/13/2003 | 5/13/2003 | A | PASS |
Troy Cobbley
|
|
|
Fire sprinkler piping is OK to cover. I notified John Venchie with Debest Fire Protection that on the second floor in both apartments that the tenting on the pipe could be improved in a couple of locations. He stated that it would be taken care of. I also said the same thing to Frank, the superintendant 5/13/2003 9:17:19 AM 5/13/2003 9:20:22 AM
|
INSP-Sprinkler Rough-in | 5/6/2003 | 5/6/2003 | 5/6/2003 | P | FAIL |
Troy Cobbley
|
|
|
The sprinkler piping and risers as installed do not match the approved plans. Resubmit plans that show as-built information. Do not cover pipe until plans have been approved and reinspected. A do not cover sticker was left at project. The east side second floor apartment plan shows 1 1/2 pipe to be installed. 1" is installed. Could not verify piping per notes #5, #6 and #7. Per review note #8 1 1/2 pipe is to be installed but 1 1/4 is installed. Resubmitt calculations. No other items inspected 5/6/2003 2:59:50 PM
|