INSP-Final Inspection | 9/4/2003 | 9/4/2003 | 9/4/2003 | P | PASS |
Troy Cobbley
|
|
|
fire sprinklers finaled
|
INSP-Sprinkler Rough-in/Hydro | 6/24/2003 | 6/25/2003 | 6/25/2003 | A | PART |
Rick Jackson
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Barbara Moore hydro on wet system okay 6/25/2003 11:15:05 AM
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2003 | 6/20/2003 | 6/20/2003 | P | PASS |
Troy Cobbley
|
|
|
Dry system and underground hydro tests are OK 6/20/2003 12:12:06 PM
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2003 | 6/19/2003 | 6/19/2003 | A | FAIL |
Troy Cobbley
|
|
|
insulation in the kitchen still has not been reinstalled 6/19/2003 10:17:32 AM
|
INSP-Sprinkler Rough-in | 6/17/2003 | 6/18/2003 | 6/18/2003 | A | CANC |
Troy Cobbley
|
|
|
doug; Phone #: ###-#### The sprinkler contractor called and cancelled the inspection due to another contractor removing the tenting insulation in the kitchen 6/18/2003 10:34:06 AM
|
INSP-Sprinkler Rough-in/Hydro | 6/17/2003 | 6/17/2003 | 6/17/2003 | P | PASS |
Troy Cobbley
|
|
|
center section piping ok to cover except for kitchen 6/17/2003 3:11:47 PM 6/17/2003 3:12:12 PM
|
INSP-Supply line flush | 6/17/2003 | 6/17/2003 | 6/17/2003 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line flush is OK 6/17/2003 9:08:28 AM
|
INSP-Sprinkler Rough-in/Hydro | 6/13/2003 | 6/16/2003 | 6/16/2003 | A | FAIL |
Troy Cobbley
|
|
|
all previous items on the correction notice have not been corrected 6/16/2003 11:04:16 AM
|
INSP-Supply line flush | 6/13/2003 | 6/16/2003 | 6/16/2003 | A | FAIL |
Troy Cobbley
|
|
|
United water did not have the underground water supply turned on so we couldn't do the test 6/16/2003 11:02:36 AM
|
INSP-Sprinkler Rough-in | 6/12/2003 | 6/13/2003 | 6/13/2003 | A | FAIL |
Troy Cobbley
|
|
|
john; Phone #: ###-#### The wet system in the west entry lobby has the incorrect pipe size. Treasure valley to resubmit calculations to prove size is ok. Upright sprinkler heads along the west wall are overspaced off the wall. Per the contractor he will have the insulation people install additional insulation. The insulation will need to be within 6'-0" of the branchline the entire lenght of the wall. Two armovers in the southeast corner of the central section will need to be lenghtened by 10" to fix an overspacing problem. The east entry wet and dry piping and the tenting is not complete yet. Sprinkler piping not to be covered 6/13/2003 12:20:20 PM
|
INSP-Supply line flush | 6/13/2003 | 6/13/2003 | 6/13/2003 | P | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 6/13/2003 at 11:16:16 AM. Contact: ###-####. per Troy the water is shut off and they won't be able to flow today 6/13/2003 3:35:26 PM
|
INSP-Sprinkler Rough-in/Hydro | 5/29/2003 | 5/29/2003 | 5/29/2003 | P | FAIL |
Troy Cobbley
|
|
|
john; Phone #: ###-#### I spoke with john the installer and left a message with cameron the superintendant that the insulation was still missing over a light fixture in the hallway and that at the south end of the building the piping is now sandwiched between insulation 5/29/2003 3:16:21 PM
|
INSP-Sprinkler Rough-in/Hydro | 5/13/2003 | 5/14/2003 | 5/14/2003 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in is ok in the north wing of the project. Sprinkler piping is OK to cover 5/14/2003 3:51:52 PM
|
INSP-Sprinkler Rough-in/Hydro | 5/11/2003 | 5/12/2003 | 5/12/2003 | P | FAIL |
Troy Cobbley
|
|
|
Hangers and sway bracing have been corrected but no insulation has been added yet. Per the contractor the insulation will be completed tomorrow and an inspection called in. 5/12/2003 4:00:19 PM
|