INSP-Final Inspection | 4/2/2004 | 4/2/2004 | 4/2/2004 | P | PASS |
Rick Jackson
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 3/29/2004 | 3/29/2004 | 3/29/2004 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 3/29/2004 at 6:53:06 AM. Contact: ###-####. tape on heads - can't verify head type 3/29/2004 2:55:07 PM
|
INSP-Final Inspection | 3/5/2004 | 3/5/2004 | 3/8/2004 | P | PART |
Rick Jackson
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Darla Downs Phase I complete; will need to verify tanning area of Phase II when this area is completed 3/8/2004 9:53:44 AM
|
INSP-Final Inspection | 3/1/2004 | 3/1/2004 | 3/1/2004 | P | PART |
Rick Jackson
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie overhead hydro okay only; need to test tampers/alarms/flow and forward flow BFP 3/1/2004 5:59:31 PM
|
INSP-Sprinkler Rough-in | 2/24/2004 | 2/24/2004 | 2/24/2004 | P | FAIL |
Rick Jackson
|
|
|
heads not installed in two areas; painted heads and heads with tape; SE area, elevator pit, electrical room not completed; no access to SW area; see plans for the above 2/24/2004 2:15:23 PM
|
INSP-Supply line flush | 2/23/2004 | 2/24/2004 | 2/24/2004 | A | PASS |
Rick Jackson
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Barbara Moore see UG permit; flush okay - still needs hydro 2/24/2004 8:16:40 AM
|
INSP-Sprinkler Rough-in | 11/13/2003 | 11/14/2003 | 11/14/2003 | P | PART |
Rick Jackson
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes womens showers and east side high bay okay 11/14/2003 4:14:28 PM
|
INSP-Sprinkler Rough-in | 10/28/2003 | 10/28/2003 | 10/28/2003 | P | PART |
Rick Jackson
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes okay to cover hard lid areas in first floor restroom; need architect verification for hanging off bottom cord of truss; need data submittal for verfication of unistrut size for 3 inch main on bottom cord - provide for field use 10/28/2003 4:07:36 PM
|