SPR Idaho Athletic Club - To install an NFPA 13 fire protection system in a new 28,600-ft/2, 2-story athletic club and related site improvements. This building contains a basketball court, swimming pool, exercise areas, locker rooms and accessory support areas. This building is constructed of reinforced concrete masonry block exterior walls with interior steel structural frame, concrete floors and metal roof deck. This building is fully fire sprinklered. All construction per the approved plans and attached comment list. The fire sprinkler system work shall comply with IFC 2000, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. The underground fire service supply is attached to FIR03-00603. This permit is attached to building permit: BLD03-01377.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/8/20041/8/20041/8/2004APASS
DetailsTroy Cobbley
INSP-Final Inspection12/30/200312/31/200312/31/2003AFAIL
DetailsTroy Cobbley
Inspection was for the sprinkler contractor completing the items on the correction notice. The sprinkler system still needs a final inspection 12/31/2003 12:29:52 PM
INSP-Supply line flush12/29/200312/30/200312/30/2003APART
DetailsTroy Cobbley
Underground flush and forward flow test of the back flow preventer is OK 12/30/2003 9:53:19 AM
INSP-Sprinkler Rough-in/Hydro12/24/200312/29/200312/29/2003APART
DetailsTroy Cobbley
Underground and Overhead hydro tests are OK. I did a rough-in inspection for the rest of the overhead sprinkler piping. Look at the city approved plans for locations that need attention. 12/29/2003 12:59:19 PM
INSP-Supply line flush12/24/200312/29/200312/29/2003PCANC
DetailsTroy Cobbley
Inspection was for a underground flush. The contractor could not get United Water there to open the valve 12/29/2003 4:44:27 PM
INSP-Sprinkler Rough-in/Hydro11/20/200311/21/200311/21/2003APART
DetailsTroy Cobbley
hard lid areas ok to cover on the first floor 11/21/2003 11:05:49 AM