INSP-Final Inspection | 6/28/2004 | 6/29/2004 | 6/29/2004 | A | PASS |
Troy Cobbley
|
|
|
Fire alarm finaled 6/29/2004 9:59:06 AM
|
INSP-Final Inspection | 6/15/2004 | 6/18/2004 | 6/18/2004 | A | FAIL |
Troy Cobbley
|
|
|
Provide a/v coverage in the corridor per the last correction notice. Change the 30cd strobe to 15cd in Rob's office. Provide signage on doors to facp and sprinkler riser per review note #23. Test low air signal on dry pipe riser 6/18/2004 9:33:41 AM
|
INSP-Final Inspection | 6/9/2004 | 6/14/2004 | 6/14/2004 | A | CANC |
Troy Cobbley
|
|
|
Inspection was cancelled by Rob with Protex 6/14/2004 8:33:34 AM
|
INSP-Final Inspection | 3/12/2004 | 3/18/2004 | 3/18/2004 | A | FAIL |
Troy Cobbley
|
|
|
Resubmit fire alarm plans that include all devices including the second dry pipe valve, backflow preventor and the additional three duct smoke detectors. End of line voltage on the notification circuits exceeds 21.6 volts(nfpa 72, 7.3.2.3). Provide verification/explanation on resubmittals on why remaining hvac units do not have automatic shutdown per IMC. Office and corridor areas that open into the new addition must be brought up to code compliance. Only the items listed above have been inspected and addressed. All other items to be verified when resubmitted plans have been issued 3/18/2004 9:41:04 AM
|
INSP-Final Inspection | 2/12/2004 | 2/12/2004 | 2/12/2004 | A | PART |
Troy Cobbley
|
|
|
Temporary occupancy was given until all of the fire mains are upgraded per plans submitted to boise city and the fire alarm system is completed
|