Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR04-00149
StatusFinaled
Name SIMPLEX/GRINNELL
Site Address 3033 W ELDER ST
Project Namealm - Wells Fargo Data Center
Customer Number 
ePlanReview 
Description
To remove a halon suppression system in a data center and replace with a double interlock pre-action system. FA Scope is to implement a releasing panel (UL listed) for a pre-action system in the data center, located in the single story building. The releasing panel will be monitoring by the existing fire alarm panel located in the 3 story building.

9/14/2004 - Additional scope is to provide notification throughout the Wells Fargo Data Center building. Three (3) new NAC extender panels are added under this permit. Smoke detectors will be provided in the computer room above the ceiling and below the ceiling for indication to the releasing panel.

The associated building permit (BLD03-03054) is to remodel and update some mechanical and electrical systems in large portions of an existing 55,732 sq. ft., one story building per approved plans on file. Work to include miscellaneous interior demolition work, new grilles/registers/diffusers, new thermostats, some new VAV boxes, new VFD and filters in mechanical room, new lighting/switching and exit signs in most of the building, and some electrical work. All circuits are connected to an existing standby generator. (BUILDING #2 is not included in the scope of the fire alarm system.- Remodel to update mechanical system in existing 116,397 sq. ft., three story building. Work to include additional steel support for two new rooftop ventilator units, sprayed fire-resistant materials at new steel members and any repairs at penetrations of new rooftop units, three new relief louvers in exterior wall at existing mechanical rooms, rebalance entire mechanical system, new VFD and filters in mechanical rooms, and some electrical work. Special Inspection required for sprayed fire-resistant materials.) This is a Scope of Work Permit. Letter of Completion to be issued when done. Plans reviewed for compliance with IBC, IECC and IFC only. NOTE: These buildings are fully fire sprinklered for area increase. (PC#0800-03) JCB. (WELLS FARGO SERVICE CENTER)(MECHANICAL UPGRADE) BUILDING #1

Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/4/20055/5/20055/5/2005PPASS
DetailsForrest France
Fire alarm finaled.
INSP-Final Inspection2/4/20052/10/20052/10/2005AFAIL
DetailsTroy Cobbley
Provide additional a/v in truck delivery on circuit av-8. Repair a/v9-3 in storage supply. Set high/low pressure switch and test. Liebert #4 does not shut down. Test supervision between new panel/nac's and the existing system. Provide map at new panel and existing panel. Remove old equipment. Resend alarm, trouble and supervisory signals to central station. Verify if existing tamper can remain on old system and if heats need to be shown on new plans. 2/10/2005 8:18:01 AM
INSP-Final Inspection2/1/20052/3/20052/3/2005PCANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 2/1/2005 at 12:34:37 PM. Contact: ###-####. cancel per Robert11/2/1/05 2:50pm BAS
INSP-Final Inspection1/28/20052/2/20052/1/2005ACANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 1/28/2005 at 10:58:06 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Feb 1 2005 12:32PM.
INSP-Final Inspection1/25/20052/1/20052/1/2005ACANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 1/25/2005 at 5:18:33 PM. Contact: ###-####.
FIR-Aging Inspection1/10/20051/10/20051/10/2005 PART
DetailsRick Jackson
This project is nearly completed and inspections will be scheduled when ready 1/10/2005 8:55:22 AM