INSP-Final Inspection | 6/1/2005 | 6/7/2005 | 6/7/2005 | P | PASS |
Forrest France
|
|
|
Fire sprinkler finaled.
|
INSP-Final Inspection | 5/25/2005 | 5/31/2005 | 5/27/2005 | P | CANC |
Troy Cobbley
|
|
|
kerry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Inspection cancelled from web by: Marsha Smylie
|
INSP-Final Inspection | 5/13/2005 | 5/16/2005 | 5/16/2005 | P | FAIL |
Forrest France
|
|
|
Two upright heads in vault are spaced too far off wall to meet OH 1 requirements for this space. Provide map at riser indicating location of auxillary drains. Provide test certificates. Verify foreward flow through BFP as required by note #59. Provide sp
|
INSP-Sprinkler Rough-in/Hydro | 2/2/2005 | 2/2/2005 | 2/2/2005 | A | PART |
Rick Jackson
|
|
|
Air test okay; need to add EQ at new main; different heads used in underfloor area; need as-builts for addition to under floor in phone room 2/2/2005 9:45:34 AM
|
INSP-Sprinkler Rough-in/Hydro | 1/31/2005 | 2/1/2005 | 2/1/2005 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 1/31/2005 at 6:43:05 PM. Contact: ###-####. Start air test at 43 psi 2/1/2005 11:17:05 AM
|
INSP-Sprinkler Rough-in/Hydro | 1/28/2005 | 1/31/2005 | 1/31/2005 | P | PART |
Rick Jackson
|
|
|
Mick; Phone #: ###-#### Internet Inspection Request from: Jan Rice hydro okay 1/31/2005 4:03:52 PM
|
FIR-Aging Inspection | 12/27/2004 | 12/27/2004 | 12/28/2004 | | PASS |
Rick Jackson
|
|
|
Talked to Roger and the work is in process and the final should be called in very soon 12/28/2004 9:30:19 AM
|