Permit Information
Permit NumberFIR04-00166
StatusFinaled
Name NORTHWEST SALES COMPANY
Site Address 999 W MAIN ST
Project NameOne Capital Center Upgrade
Customer Number 
ePlanReview 
Description
1/27/2005 - To upgrade the fire alarm control panel and associated floors as required for a highrise in the IFC. Per the upgrade agreement, the 1st, 3rd, 8th floors (tenant and cores) and penthouse will be completed by March 31, 2005. The elevator controls and penthouse were completed under this permit number, 9/1/2004. The 3rd floor was completed under FIR04-00645 (finaled; 11/24/2004). The 3rd floor drawings show the modifications (smoke detectors for door release and two-way telephone jacks, for fire service use only) that will require testing.

The new fire alarm system will be code compliant with IFC 2000 and NFPA 72, 2002.

FIR05-00048 is associated with building permit (BLD 03-02347) is to remodel a 7,279 square foot area within an existing whole floor (17,050 square foot) office tenant. A demolition permit (BLD03-02473) was issued earlier. A portion of the existing 2-hr fire barrier that functions as a horizontal exit is being modified. Work is to include interior nonbearing walls, suspended ceilings, interior doors, and interior finishes all per the approved drawings and plan review report on file. The location of fire sprinkler heads shall comply with NFPA 13-1999 as regulated by the Fire Department. **CJW** (QWEST - ONE CAPITAL CENTER - 8TH FLR) This building is fire sprinklered because it is a high-rise.

The original fire alarm upgrade agreement will be superseded by a new fire alarm upgrade agreement. (Jeremy Malone, 336-4781, is the contact for the agreement). At this time, the elevator controls have been upgraded and require the code compliant elevator recall/shutdown per NFPA 72. (Dave Miller, BFD, agrees that the alarm portion needs to be completed.) The fire alarm hardware will be connected to the existing Cerberus FACP to expedite the elevator upgrade. The expectation is that the elevator controls will be included in the initial phase of the fire alarm system upgrade.

This permit will include the elevator control upgrade and the fire alarm components defined to be installed during the first year of the revised fire alarm upgrade agreement. The write up will be split between each portion for general comments and resubmittal items and titled with the date of the review.

The original upgrade agreement will be scanned and attached to this permit in Tidemark. The revised upgrade agreement will also be scanned and attached to this permit in Tidemark.

There is no associated building permit.

Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/26/20066/28/20066/28/2006APASS
DetailsForrest France
Required corrections have been completed, fire alarm work is satisfactory, permit finaled.
INSP-Alarm Testing2/28/20063/3/20063/3/2006APART
DetailsForrest France
Provide resubmittals for changes in the basement (Angels), provide updated building map, add notification in the break room on 8th floor.
INSP-Alarm Testing2/13/20062/16/20062/16/2006ACANC
DetailsForrest France
would like it at 8AM if possible let me know. Internet Inspection Request from: Rick Groom Inspection cancelled from web by: Rick Groom
INSP-Alarm Testing2/6/20062/9/20062/8/2006ACANC
DetailsTroy Cobbley
WOULD LIKE TO DO THIS AT 8AM IF POSSIBLE, IF NOT LET ME KNOW... Internet Inspection Request from: Rick Groom Inspection cancelled from web by: Rick Groom
INSP-Alarm Testing1/24/20061/25/20061/25/2006APART
DetailsForrest France
Tested functionality of the notification and voice evac systems only, approved plans for the 8th floor not available for review.
INSP-Alarm Testing1/11/20061/18/20061/11/2006ACANC
DetailsForrest France
COULD TAKE ALL DAY, MAYBE 2 DAYS... Internet Inspection Request from: Rick Groom Inspection cancelled from web by: Rick Groom
INSP-Final Inspection1/27/20051/27/20051/27/2005APART
DetailsRick Jackson
All items have been corrected from previous inspection 1/27/2005 8:30:39 AM
INSP-Alarm Testing10/14/200410/15/200410/15/2004AFAIL
DetailsRick Jackson
Rick we need to schedule this for 7am let me know if this will work for you... Internet Inspection Request from: Rick Groom Need updated maps; relocate detector on first floor away from diffuser; batteries per plans; need penthouse plans; smoke above panel 10/15/2004 9:37:30 AM