INSP-Final Inspection | 9/14/2005 | 9/14/2005 | 9/14/2005 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 7/15/2005 | 7/15/2005 | 7/15/2005 | P | PART |
Forrest France
|
|
|
Provide seismic clearance at UG supply where it passes through the foundation wall, provide sinage at riser room door indicating its location.
|
INSP-Final Inspection | 6/21/2005 | 6/22/2005 | 6/22/2005 | A | PART |
Forrest France
|
|
|
Final pending inspection of heads in one room at the basement level to which access was denied, also need to provide seismic clearance at the underground supply where it passes through the foundation wall.
|
INSP-Sprinkler Rough-in/Hydro | 6/8/2005 | 6/8/2005 | 6/8/2005 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test of basement, first floor, and antifreeze systems passed two hour test.
|
INSP-Sprinkler Rough-in | 4/11/2005 | 4/11/2005 | 4/11/2005 | P | PART |
Troy Cobbley
|
|
|
See plans with todays date for areas ok to cover. Resubmittals are required for changes in piping, lobby and room above ceiling
|
INSP-Sprinkler Rough-in | 3/23/2005 | 3/23/2005 | 3/23/2005 | P | PASS |
Troy Cobbley
|
|
|
Spoke to Mike on phone. Area in question on first floor is ok to cover 3/23/2005 4:00:54 PM
|
INSP-Sprinkler Rough-in | 2/25/2005 | 2/25/2005 | 2/25/2005 | P | PART |
Troy Cobbley
|
|
|
See approved plans for locations in basement where the sprinkler piping is ok to cover. 2/25/2005 3:28:01 PM
|
INSP-Sprinkler Rough-in | 2/14/2005 | 2/14/2005 | 2/14/2005 | P | PART |
Troy Cobbley
|
|
|
See approved plans for first floor locations ok to cover 2/14/2005 4:07:28 PM
|
INSP-Sprinkler Rough-in | 2/1/2005 | 2/2/2005 | 2/2/2005 | P | PART |
Rick Jackson
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Barbara Moore 2nd and 3rd floors hydro and r/i's all complete 2/2/2005 1:51:23 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/31/2005 | 1/31/2005 | 1/31/2005 | P | PART |
Rick Jackson
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Jan Rice 2nd floor r/i and hydro okay 1/31/2005 3:11:11 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/19/2004 | 10/19/2004 | 10/19/2004 | P | PART |
Rick Jackson
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Hydro okay on third floor and main feed from riser to third floor; still need resubmittals and will need to verify piping after approved 10/19/2004 3:39:55 PM
|
INSP-Sprinkler Rough-in | 10/15/2004 | 10/15/2004 | 10/15/2004 | P | FAIL |
Rick Jackson
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Verified piping on third floor hallway only - need resubmittals due to changes and using flexheads 10/15/2004 1:54:01 PM
|
INSP-Conference | 8/26/2004 | 8/26/2004 | 8/26/2004 | P | PART |
Rick Jackson
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Met with Mike about the riser for floors - plans show in electrical closet but will not meet clearances from electrical panels per NEC; stair risers may work but will have to maintain IBC clearances at landings; plan modifications will be needed to reflect changes 8/26/2004 1:03:51 PM
|